PLAN CHECK COMMENTS
COMMENTS
Planning & Building Agency
Building Safety Division
20 Civic Center Plaza
P.O. Box 1988 (M-19)
Santa Ana, CA 92702
(714) 647-5800
www.santa-ana.org
PLAN CHECK NO:
10195925
PROJECT ADDRESS:
1015 S Fairview St
PLAN CHECK ENGINEER:
Ahangian, KathyTEL:714
647-5812FAX:714
647-5897
TYPE OF CONSTRUCTION:
V B
OCCUPANCY CLASSIFICATION(S):
M
PLAN CHECK DATES:
REMARKS/RECHECK ITEMS:
APPLICATION
3/22/2018
INITIAL REVIEW
4/3/2018
EXPIRATION
9/18/2018
RECHECKS:
1.
PROJECT APPLICANT CONTACT PERSON:
2.
Alfredo Rodriguez
3.
TEL:
(909)374-2597
FAX:
VALUATION:$50,000.00
EMAIL:
FLOOD ZONE:X-0602320256J
APPLICABLE CODE: 2016 CALIFORNIA BUILDING CODE (CBC) WITH
CITY OF SANTA ANA AMENDMENTS
All items noted on this plan check report must be addressed. If you feel that an item is not applicable to your project, note “N/A” and discuss the reason with the plan checker.Please indicate the sheet number and detail to the right of each correction, or note the number on the plans where the correction is made. Resubmit marked original, calculations and this correction sheet. A separate sheet for response may be used.Resubmit 2corrected sets of plans.Meetings between the project applicant/designer and the plan reviewer shall be by appointment only. Please call (714) 647-5812 for an appointment.Please return marked up set of drawings with corrections.Please identify type of the business on the plans.Clearly indicate the scope of work under this building permit application:
- Revise project job description on the building permit application worksheet to reflect the work to be done
under the subject building permit application. Note type of the work on the drawings.
- Construction drawings must clearly show all work to be done under the subject building permit application.All persons preparing plans, specifications, and instruments of service for others shall sign those plans, specifications and other instruments of service for others shall sign those plans, specifications and other instruments of service and all contracts therefore. This requirement applies to both exempt and non-exempt projects. Business and Professions Code Chapter 3, Division 3, Section 5536.1(a).Include address and telephone number of the responsible designer, and date of signing of drawings.This review does not include mechanical, plumbing, fire sprinkler system, or electrical work. Separate plans, applications, fees, plan checks, and permits are required for mechanical, plumbing, fire sprinkler systems, and electrical work. Call 647-5800 for information.Please remove all Plumbing, Electrical and Mechanical drawings.The applicant shall obtain clearances/approvals for the following prior to building permit issuance:
- Planning Division approval on the corrected/final set of drawings (647-5804.) Previously approved plans
should be submitted to expedite the process.
- Public Works Agency approval (647-5039)
- County of Orange Health Department approval on the corrected/final set of drawings ((714)433-6000)
- Proof of Worker’s Compensation Insurance shall be required at the time of permit issuanceSubmit a signed copy of the contract showing labor and materials for all work to be done under the subject building permit application. The plan check engineer may accept the contract price as the valuation of improvements for unique/unusual projects in lieu of using a cost per square foot basis.Drawings must be to scale and be on 18” x 24” minimum sheets.
- Provide a Vicinity Map showing project location
- Scale of Drawings must be large enough to ensure legibility
- Show North Arrow on Plan ViewsProvide the following:
- Provide a fully dimensioned site plan on each set of plans.
- Disabled access compliance must be shown on the site plan.Provide existing floor plan.Provide ICC report for the Walk in cooler.Show on the plans:
- Type of Construction is VBProvide on the drawings a complete door schedule, showing:
- Hardware complying with exiting and disabled accessibility requirements (CBC Sections 1008.1.8 and
1133B.2.5)Hand-activated door opening hardware shall be centered between 30” and 44” above the floor. Latching and locking doors that are hand activated and which are in a path of travel shall be operable with a single effort by lever-type hardware, by panic bars, push-pull activating bars, or other hardware designed to provide passage without requiring the ability to grasp the opening hardware. Locked exit doors shall operate as above in egress direction.Note on the drawings: “Maximum effort to operate doors shall not exceed 5 pounds for exterior doors and interior doors, such pull or push effort being applied at right angles to hinged doors and at the center place of sliding or folding doors. Compensating devices or automatic door operators may be utilized to meet the above standards. When fire doors are required, the maximum effort to operate the door may be increased to the minimum allowable by the appropriate administrative authority, not to exceed 15 pounds.Exit illumination and exit sign requirements in accordance with CBC Section 1011 shall be shown on the drawings. Be specific as to the type of exit signs to be installed.Tactile exit signs shall be required at the following locations:
- Each grade-level exterior exit door shall be identified by a tactile exit with the word “EXIT.”
- Each exit door that leads directly to a grade-level exterior exit by means of an exit enclosure, or an exit
passageway, shall be identified by a tactile exit sign with the words “EXIT ROUTE.”
- Each exit door through a horizontal exit shall be identified by a sign with the words “TO EXIT.”It is the project designer’s/property owner’s responsibility to show compliance on the drawings with all applicable Federal and State Accessibility Standards.Drawings submitted to the Building Division for review shall provide the following information to insure compliance with CBC Section 1134B/Chapter 11B:
- An accessible entrance
- An accessible route to the altered area
- Accessible restrooms
- Accessible telephone (if any)
- Accessible drinking fountains, and
- Parking, signage and alarmsShow toilet is in compliance with CBC 11B-604.3.Provide path of travel from disabled parking and public way to the building , including but not limited to curb ramps, truncated dome,…If a walk crosses or adjoins a vehicular way, and the walking surfaces are not separated by curbs, railings or other elements between the pedestrian areas and vehicular areas, the boundary between the areas shall be defined by a continuous detectable warning which is 36” wide, complying with the CBC 11B Detectable Warning Product Approval. Only approved Division of the State Architect, Access Compliance (DSA/AC) approved detectable warning products and directional surfaces shall be installed in accordance with CBC Section 1133B.8.5.Complete the attached Disabled Accessibility Documentation Form.Show height of the partition walls.Provide water heater anchor straps within the upper and lower 1/ 3.