PLAN CHECK COMMENTS
COMMENTS
Planning & Building Agency
Building Safety Division
20 Civic Center Plaza
P.O. Box 1988 (M-19)
Santa Ana, CA 92702
(714) 647-5800
www.santa-ana.org
PLAN CHECK NO:
10196697
PROJECT ADDRESS:
1951 E Dyer Rd
PLAN CHECK ENGINEER:
Chehade, NabilTEL:714
647-5848FAX:714
647-5897
TYPE OF CONSTRUCTION:
III A, SPK
OCCUPANCY CLASSIFICATION(S):
R-2
PLAN CHECK DATES:
REMARKS/RECHECK ITEMS:
APPLICATION
6/11/2018
INITIAL REVIEW
7/31/2018
EXPIRATION
12/8/2018
RECHECKS:
1.
PROJECT APPLICANT CONTACT PERSON:
2.
Brandon Bertoglio
3.
TEL:
(714)271-9370
FAX:
VALUATION:
EMAIL:
bbertoglio@allresco.com
FLOOD ZONE:X-0602320278J
APPLICABLE CODE: 2010 CALIFORNIA BUILDING CODE (CBC) WITH
CITY OF SANTA ANA AMENDMENTS
All items noted on this plan check report must be addressed. If you feel that an item is not applicable to your project, note “N/A” and discuss the reason with the plan checker.Please indicate the sheet number and detail to the right of each correction, or note the number on the plans where the correction is made. Resubmit marked original, calculations and this correction sheet. A separate sheet for response may be used.The cumulative loads on the anchor bolts, both tension and compression, are high in certain areas. There is a note on the holdown plans indicating that the design of the anchor bolt connection to the structure is to be done by the engineer of record. Please provide design calcs and make sure the holdown plans, reference the details provided on the original set of plans, for such connection.