HomeMy WebLinkAbout245014_1_Corrections.docxRESIDENTIAL PLAN CHECK
COMMENTS
Planning & Building Agency
Building Safety Division
20 Civic Center Plaza
P.O. Box 1988 (M-19)
Santa Ana, CA 92702
(714) 647-5800
www.santa-ana.org
PLAN CHECK NO:
10197444
PROJECT ADDRESS:
714 E Grovemont St
PLAN CHECK ENGINEER:
So, AnsonTEL:714
647-5830FAX:714
647-5897
TYPE OF CONSTRUCTION:
V B
OCCUPANCY CLASSIFICATION(S):
U
PLAN CHECK DATES:
REMARKS/RECHECK ITEMS:
APPLICATION
8/21/2018
INITIAL REVIEW
9/27/2018
EXPIRATION
2/17/2019
RECHECKS:
1.
PROJECT APPLICANT CONTACT PERSON:
2.
Marcos Cortez
3.
TEL:
(714)873-4969
FAX:
VALUATION: $25,000.00
EMAIL:
oc@ocprintingservices.com
FLOOD ZONE: X-0602320163J
Note: Numbers in parenthesis (unless otherwise noted) refer to code sections of the 2016 California Residential Code (CRC); 2016 California Building Code (CBC); CMC = 2016 California Mechanical Code; CPC = 2016 California Plumbing Code; CEC = 2016 California Electrical Code; T = Table; ICC = International Code Council.All items noted on this plan check report must be addressed. If you feel that an item is not applicable to your project, note “N/A” and discuss the reason with the plan checker.Please indicate the sheet number and detail to the right of each correction, or note the number on the plans where the correction is made. Resubmit marked original, calculations and this correction sheet. A separate sheet for response may be used.Resubmit 3corrected sets of plans.Meetings between the project applicant/designer and the plan reviewer shall be by appointment only. Please call (714) 647-5830 for an appointment.The drawings/information submitted for Building Safety Division review is incomplete. The applicant shall, prior to resubmitting, complete all construction documents to show compliance with the 2016 California Building Standards Code with local amendments and to clearly indicate the scope of work under this building permit application. There may be additional requirements when complete construction drawings and supporting data is submitted for Building Safety Division review.Sheet 3Provide information on manufacture fireplace and chimney. Product shall have approved-listing report such as underwriting laboratories report, or ICC report, or other testing agency.Engineer shall design and specify the structural connection between the fireplace structure and footing. Consider seismic loading on over-turning anchorage design.Engineer shall stamp and sign all structural drawings and the first page of structural calculations.The patio cover structure has been reviewed and there are no review comments.