HomeMy WebLinkAbout246467_2_Corrections.docxRESIDENTIAL PLAN CHECK
COMMENTS
Planning & Building Agency
Building Safety Division
20 Civic Center Plaza
P.O. Box 1988 (M-19)
Santa Ana, CA 92702
(714) 647-5800
www.santa-ana.org
PLAN CHECK NO:
10197883
PROJECT ADDRESS:
1584 E Santa Clara Ave
PLAN CHECK ENGINEER:
Heidari, FredTEL:714
647-5862FAX:714
647-5897
TYPE OF CONSTRUCTION:
N/A
OCCUPANCY CLASSIFICATION(S):
U
PLAN CHECK DATES:
REMARKS/RECHECK ITEMS:
APPLICATION
10/1/2018
INITIAL REVIEW
10/9/2018
EXPIRATION
3/30/2019
RECHECKS:
1. 10/16/2018
PROJECT APPLICANT CONTACT PERSON:
2.
Brandon Coughlin
3.
TEL:
(949)382-8216
FAX:
VALUATION:$0.01
EMAIL:
FLOOD ZONE:X-0602320163J
The recheck of your drawings was completed this morning, 10-16-2018; and they are approved for building permit issuance subject to approvals required under item # 8 below and the drawing sheet: “W -3” to be signed by the engineer of records for the walls,
Approved drawings are placed at the plan check counter for your convenience.All items noted on this plan check report must be addressed. If you feel that an item is not applicable to your project, note “N/A” and discuss the reason with the plan checker.Please indicate the sheet number and detail to the right of each correction, or note the number on the plans where the correction is made. Resubmit marked original, calculations and this correction sheet. A separate sheet for response may be used.Resubmit 2corrected sets of plans.Meetings between the project applicant/designer and the plan reviewer shall be by appointment only. Please call (714) 647-5862 for an appointment.The drawings/information submitted for Building Safety Division review is incomplete. The applicant shall, prior to resubmitting, complete all construction documents to show compliance with the 2016 California Building Standards Code with local amendments and to clearly indicate the scope of work under this building permit application. There may be additional requirements when complete construction drawings and supporting data is submitted for Building Safety Division review.Submitted drawing is not clear of the nature of this building permit. There is no scope of work on the drawings. The job description on the building permit application is left blank. The plan check stopped due to items 5 & 6 above.
The applicant shall obtain clearances/approvals for the following, prior to building permit issuance:
-Planning Division approval on the corrected/final set of drawings (647-5804). Previously
approved plans should be submitted to expedite the process.
- Public Works Agency approval (647-5039).
- Proof of Worker's Compensation Insurance shall be required at the time of permit issuance.