HomeMy WebLinkAbout245113_3_Corrections.docxTENANT IMPROVEMENT
PLAN CHECK COMMENTS
COMMENTS
Planning & Building Agency
Building Safety Division
20 Civic Center Plaza
P.O. Box 1988 (M-19)
Santa Ana, CA 92702
(714) 647-5800
www.santa-ana.org
PLAN CHECK NO:
10197478
PROJECT ADDRESS:
2841 W MacArthur Blvd Unit# D
PLAN CHECK ENGINEER:
Ahangian, KathyTEL:714
647-5812FAX:714
647-5897
TYPE OF CONSTRUCTION:
V B, SPK
OCCUPANCY CLASSIFICATION(S):
B
PLAN CHECK DATES:
REMARKS/RECHECK ITEMS:
APPLICATION
8/23/2018
INITIAL REVIEW
9/1/2018
EXPIRATION
2/19/2019
RECHECKS:
1.
PROJECT APPLICANT CONTACT PERSON:
2.
David Kang
3.
TEL:
(949)533-4119
FAX:
VALUATION:$80,000.00
EMAIL:
dkang@cdieng.com
FLOOD ZONE:X-0602320258J
APPLICABLE CODE: 2016 CALIFORNIA BUILDING CODE (CBC) WITH
CITY OF SANTA ANA AMENDMENTS
All items noted on this plan check report must be addressed. If you feel that an item is not applicable to your project, note “N/A” and discuss the reason with the plan checker.Please indicate the sheet number and detail to the right of each correction, or note the number on the plans where the correction is made. Resubmit marked original, calculations and this correction sheet. A separate sheet for response may be used.Resubmit 2corrected sets of plans.Meetings between the project applicant/designer and the plan reviewer shall be by appointment only. Please call (714) 647-5812 for an appointment.Please return marked up set of drawings with corrections.CBC Sections A106.1 and A106.3.4.1, All drawings and supporting documents shall be prepared, stamped and signed by a California licensed architect or registered civil engineer.All persons preparing plans, specifications, and instruments of service for others shall sign those plans, specifications and other instruments of service for others shall sign those plans, specifications and other instruments of service and all contracts therefore. This requirement applies to both exempt and non-exempt projects. Business and Professions Code Chapter 3, Division 3, Section 5536.1(a).This review does not include mechanical, plumbing, fire sprinkler system, or electrical work. Separate plans, applications, fees, plan checks, and permits are required for mechanical, plumbing, fire sprinkler systems, and electrical work. Call 647-5800 for information.The applicant shall obtain clearances/approvals for the following prior to building permit issuance:
- Planning Division approval on the corrected/final set of drawings (647-5804.) Previously approved plans
should be submitted to expedite the process.
- Public Works Agency approval (647-5039)
- County of Orange Health Department approval on the corrected/final set of drawings ((714)433-6000)
- Proof of Worker’s Compensation Insurance shall be required at the time of permit issuanceProvide the following:
- Provide a fully dimensioned site plan on each set of plans.
- Disabled access compliance must be shown on the site plan.
- Show all property lines of record on the site plan. Show compliance with CBC Section 704 and CBC Tables
601, 602, and 704.8.Provide path of travel from the parking to the entrance to show compliance with , including curb ramps, landing, truncated dome….Show existing floor plan.Provide a wall legend indicating whether the wall is:
- Existing, new, or to be removedCBC Section 11B404.2.7, Hand-activated door opening hardware shall be centered between 30” and 44” above the floor. Latching and locking doors that are hand activated and which are in a path of travel shall be operable with a single effort by lever-type hardware, by panic bars, push-pull activating bars, or other hardware designed to provide passage without requiring the ability to grasp the opening hardware. Locked exit doors shall operate as above in egress direction.CBC Section 11B404.2.9, Note on the drawings: “Maximum effort to operate doors shall not exceed 5 pounds for exterior doors and interior doors, such pull or push effort being applied at right angles to hinged doors and at the center place of sliding or folding doors. Compensating devices or automatic door operators may be utilized to meet the above standards. When fire doors are required, the maximum effort to operate the door may be increased to the minimum allowable by the appropriate administrative authority, not to exceed 15 pounds.Show path of travel to walk in cooler is in compliance with accessibility.Please verify if the walk-in-cooler is prefabricated or custom built. For pre-fabricated provide ICC report, and for custom built provide construction detail.It is the project designer’s/property owner’s responsibility to show compliance on the drawings with all applicable Federal and State Accessibility Standards.Drawings submitted to the Building Division for review shall provide the following information to insure compliance with CBC Section 11B-202.4
- An accessible entrance
- An accessible route to the altered area
- Accessible restrooms
- Accessible telephone (if any)
- Accessible drinking fountains, and
- Parking, signage and alarmsIf a walk crosses or adjoins a vehicular way, and the walking surfaces are not separated by curbs, railings or other elements between the pedestrian areas and vehicular areas, the boundary between the areas shall be defined by a continuous detectable warning which is 36” wide, complying with the CBC Section 11B-247.1.2.5
Detectable Warning Product Approval. Only approved Division of the State Architect, Access Compliance (DSA/AC) approved detectable warning products and directional surfaces shall be installed in accordance with CBC 11BCBC Section 11B606.5. Note on the drawings hot water and drain pipes under lavatory shall be insulated.Provide minimum 59” clear for floor mounted toilet in compartment CBC 604.3.No pictogram allowed for the bathroom door.All dining, banquet, and bar facilities shall be made accessible to persons with disabilities as provided in CBC Section 11B-226.1.. At least 5%, but not less than one of the seating spaces in each functional area is accessible as follows:
- Provide a minimum 30” x 48” wheelchair clear floor space.
- Provide knee space at tables at least 27” high, 30” wide and 19” deep.
- Provide height of tables between 28” – 34” from the floor ground.
- Provide access to accessible seating space(s) by aisles with a minimum of 36” in width.Complete the attached Disabled Accessibility Documentation Form.Provide detail for full height wall and cross reference details to show how it is supported at the top and bottom.Provide framing detail for bathroom ceiling.Provide complete structural calculations and drawings for suspended ceiling systems showing compliance with CBC Sections 711.3.1, 803.9, 1613, and 1705 (special inspections) and ASTM C635 and ASTM C636. (OR PLEASE SEE COMMENT #28 to #30)Provide a complete suspended ceiling system plan and section detail showing the following:
- Vertical supports
- Seismic wires
- Seismic strut/Compression strut
- Perimeter wires
- Separate fixture wires for lights and mechanical devices
- ICC Research Report number for the suspended ceilingThe reflected ceiling plan and details must show compliance with CBC Sections 711.3.1, 803, 1613, and 1705 (special inspection) for suspended ceiling systems.Note ICC Research Report Number on the drawings for the suspended ceiling system. (ICC Report Number 1308)