HomeMy WebLinkAbout247931_1_Corrections.docxTENANT IMPROVEMENT
PLAN CHECK COMMENTS
COMMENTS
Planning & Building Agency
Building Safety Division
20 Civic Center Plaza
P.O. Box 1988 (M-19)
Santa Ana, CA 92702
(714) 647-5800
www.santa-ana.org
PLAN CHECK NO:
10198309
PROJECT ADDRESS:
3144 W Adams St
PLAN CHECK ENGINEER:
Ahangian, KathyTEL:714
647-5812FAX:714
647-5897
TYPE OF CONSTRUCTION:
III B, SPK
OCCUPANCY CLASSIFICATION(S):
B
PLAN CHECK DATES:
REMARKS/RECHECK ITEMS:
APPLICATION
11/8/2018
INITIAL REVIEW
11/19/2018
EXPIRATION
5/7/2019
RECHECKS:
1.
PROJECT APPLICANT CONTACT PERSON:
2.
Junita Miranda
3.
TEL:
(562)735-9416
FAX:
VALUATION:$50,000.00
EMAIL:
juanitajoaquin@gmail.com
FLOOD ZONE:X-0602320258J
APPLICABLE CODE: 2016 CALIFORNIA BUILDING CODE (CBC) WITH
CITY OF SANTA ANA AMENDMENTS
All items noted on this plan check report must be addressed. If you feel that an item is not applicable to your project, note “N/A” and discuss the reason with the plan checker.Please indicate the sheet number and detail to the right of each correction, or note the number on the plans where the correction is made. Resubmit marked original, calculations and this correction sheet. A separate sheet for response may be used.Resubmit 2corrected sets of plans.Meetings between the project applicant/designer and the plan reviewer shall be by appointment only. Please call (714) 647-5812 for an appointment.Please return marked up set of drawings with corrections.The applicant shall obtain clearances/approvals for the following prior to building permit issuance:
- Planning Division approval on the corrected/final set of drawings (647-5804.) Previously approved plans
should be submitted to expedite the process.
- Police Department approval on the corrected/final set of drawings (647-5840)
- Public Works Agency approval (647-5039)
- Proof of Worker’s Compensation Insurance shall be required at the time of permit issuanceSubmit a signed copy of the contract showing labor and materials for all work to be done under the subject building permit application. The plan check engineer may accept the contract price as the valuation of improvements for unique/unusual projects in lieu of using a cost per square foot basis.Owner shall provide a letter to Building official states” Building will not be occupied before submitting drawings for tenant improvement review and final inspection”.Is double door being removed? If it is please provide framing plan to fill it in and also show all the other exit doors.Provide detail for framing the roof opening after removing all the roof top units, including sheathing and water proofing.Please make a note on the drawings, removing of structural wall and columns shown on sheet A1.21 are not part of structural support for existing shell.Show height of the building is being removed on sheet A2.11 , to determine if pedestrian protection is required.