HomeMy WebLinkAbout251055_1_Corrections.docxTENANT IMPROVEMENT
PLAN CHECK COMMENTS
COMMENTS
Planning & Building Agency
Building Safety Division
20 Civic Center Plaza
P.O. Box 1988 (M-19)
Santa Ana, CA 92702
(714) 647-5800
www.santa-ana.org
PLAN CHECK NO:
10199263
PROJECT ADDRESS:
2323 W First St
PLAN CHECK ENGINEER:
Chehade, NabilTEL:714
647-5848FAX:714
647-5897
TYPE OF CONSTRUCTION:
V B, SPK
OCCUPANCY CLASSIFICATION(S):
B
PLAN CHECK DATES:
REMARKS/RECHECK ITEMS:
APPLICATION
2/21/2019
INITIAL REVIEW
3/2/2019
EXPIRATION
8/20/2019
RECHECKS:
1.
PROJECT APPLICANT CONTACT PERSON:
2.
Daniel B. Beauchamp
3.
TEL:
(949)727-3840
FAX:
VALUATION:$20,000.00
EMAIL:
danb@beauchamparchitects.com
FLOOD ZONE:X-0602320257J
APPLICABLE CODE: 2016 CALIFORNIA BUILDING CODE (CBC) WITH
CITY OF SANTA ANA AMENDMENTS
All items noted on this plan check report must be addressed. If you feel that an item is not applicable to your project, note “N/A” and discuss the reason with the plan checker.Please indicate the sheet number and detail to the right of each correction, or note the number on the plans where the correction is made. Resubmit marked original, calculations and this correction sheet. A separate sheet for response may be used.Resubmit 2corrected sets of plans.Meetings between the project applicant/designer and the plan reviewer shall be by appointment only. Please call (714) 647-5848 for an appointment.This review does not include mechanical, plumbing, fire sprinkler system, or electrical work. Separate plans, applications, fees, plan checks, and permits are required for mechanical, plumbing, fire sprinkler systems, and electrical work. Call 647-5800 for information.The applicant shall obtain clearances/approvals for the following prior to building permit issuance:
- Planning Division approval on the corrected/final set of drawings (647-5804.) Previously approved plans
should be submitted to expedite the process.
- Fire Department approval on the corrected/final sets of drawings ((714)573-6100)
- Police Department approval on the corrected/final set of drawings (647-5840)
- Public Works Agency approval (647-5039)Plans should be submitted to the fire department to ensure that the sprinkler system is operational.Please note fire repair triggers compliance with the accessibility requirements. Pass of travel to the area of remodel and bathrooms serving the area of remodel need to comply. Any new work should comply with the accessibility requirements. Provide plans, details etc to show that the bathrooms are in compliance.Detail 2 on S1 notch the mansard rafter to get a full bearing on the 4X beam.