HomeMy WebLinkAbout253042_3_Corrections.docxTENANT IMPROVEMENT
PLAN CHECK COMMENTS
COMMENTS
Planning & Building Agency
Building Safety Division
20 Civic Center Plaza
P.O. Box 1988 (M-19)
Santa Ana, CA 92702
(714) 647-5800
www.santa-ana.org
PLAN CHECK NO:
10199937
PROJECT ADDRESS:
3430 W Maywood Ave
PLAN CHECK ENGINEER:
Ahangian, KathyTEL:714
647-5812FAX:714
647-5897
TYPE OF CONSTRUCTION:
III B
OCCUPANCY CLASSIFICATION(S):
F-1
PLAN CHECK DATES:
REMARKS/RECHECK ITEMS:
APPLICATION
4/26/2019
INITIAL REVIEW
5/11/2019
EXPIRATION
10/23/2019
ECHECKS:
1.
PROJECT APPLICANT CONTACT PERSON:
2.
Tom Riggins
3.
TEL:
(714)953-6333
FAX:
(714)543-7601
VALUATION:$67,200.00
EMAIL:
triggins@rigginsconst.com
FLOOD ZONE:X-0602320258J
APPLICABLE CODE: 2016 CALIFORNIA BUILDING CODE (CBC) WITH
CITY OF SANTA ANA AMENDMENTS
All items noted on this plan check report must be addressed. If you feel that an item is not applicable to your project, note “N/A” and discuss the reason with the plan checker.Please indicate the sheet number and detail to the right of each correction, or note the number on the plans where the correction is made. Resubmit marked original, calculations and this correction sheet. A separate sheet for response may be used.Resubmit 2corrected sets of plans.Meetings between the project applicant/designer and the plan reviewer shall be by appointment only. Please call (714) 647-5812 for an appointment.Please return marked up set of drawings with corrections.This review does not include mechanical, plumbing, fire sprinkler system, or electrical work. Separate plans, applications, fees, plan checks, and permits are required for mechanical, plumbing, fire sprinkler systems, and electrical work. Call 647-5800 for information.The applicant shall obtain clearances/approvals for the following prior to building permit issuance:
- Planning Division approval on the corrected/final set of drawings (647-5804.) Previously approved plans
should be submitted to expedite the process.
- Fire Department approval on the corrected/final sets of drawings ((714)573-6100)
- Police Department approval on the corrected/final set of drawings (647-5840)
- Public Works Agency approval (647-5039)
- Proof of Worker’s Compensation Insurance shall be required at the time of permit issuancePlease Note type of the business on the cover sheet.Submit a signed copy of the contract showing labor and materials for all work to be done under the subject building permit application. The plan check engineer may accept the contract price as the valuation of improvements for unique/unusual projects in lieu of using a cost per square foot basis.Submit a letter addressed to the Building Safety Division describing in detail the manufacturing process from material delivery, storage, handling, packaging, and shipping of finish product. Include an equipment list describing use in the process.Indicate detail and section references as to their appropriate location on plan view.Provide typical section view detail of all new partitions and ceilings showing:-Provide span table for metal studs.Provide complying exiting plan for the Entire Building.Table 1017.1 Exit Access Travel Distance:
OCCUPANCYWITHOUT SPRINKLERWITH SPRINKLERSYSTEM (feet)SYSTEM (feet)
A, E, F-1, I-1, M, R, S-1200250b
B200300c
F-2, S-2, U300400c
H-1Not Permitted75c
H-2Not Permitted100c
H-3Not Permitted150c
H-4Not Permitted175c
H-5Not Permitted200cTable 1006.3.2(2) For Buildings With One Exit:Maximum HeightMaximum OccupantsOf Building(Or Dwelling Units)OccupancyAbove Grade PlanePer Floor And Travel Distance
A, B, E, F, M, U1 Story49 occupants and 75’ travel distance
H-2, H-3, L1 Story3 occupants and 25’ travel distance
H-4, H-5, I, R1 Story10 occupants and 75’ travel distance
S1 Story29 occupants and 100’ travel distance
B, F, M, S2 Stories29 occupants and 75’ travel distanceCBC Sections 1028.5, EXIT DISCHARGE. That portion of a means of egress system between the termination of an exit and a public way.Tactile exit signs shall be required at the following locations:
- Each grade-level exterior exit door shall be identified by a tactile exit with the word “EXIT.”
- Each exit door that leads directly to a grade-level exterior exit by means of a stairway or ramp shall be
identified by a tactile exit sign with the following words as appropriate:“EXIT STAIR DOWN”“EXIT RAMP DOWN”“EXIT STAIR UP”“EXIT RAMP UP”
- Each exit door that leads directly to a grade-level exterior exit by means of an exit enclosure, or an exit
passageway, shall be identified by a tactile exit sign with the words “EXIT ROUTE.”
- Each exit access door from an interior room or area to a corridor or hallway, which is required to have a visual
exit sign, shall be identified by a tactile exit sign with the words “EXIT ROUTE.”
- Each exit door through a horizontal exit shall be identified by a sign with the words “TO EXIT.”Drawings submitted to the Building Division for review shall provide the following information to insure compliance with CBC Section 11B-202.4:
- An accessible entrance
- An accessible route to the altered area
- Accessible restrooms
- Accessible telephone (if any)
- Accessible drinking fountains, and
- Parking, signage and alarmsPlease fillout attached Accessible compliance form.Provide 18” clearance to the strike edge of Bathroom door for 60” clear length.If a walk crosses or adjoins a vehicular way, and the walking surfaces are not separated by curbs, railings or other elements between the pedestrian areas and vehicular areas, the boundary between the areas shall be defined by a continuous detectable warning which is 36” wide, complying with the CBC Section 11B-247.1.2.5Please verify if there is any curb ramp.Detail 6/A-8 referenced on sheet A-2.1 is not included. Provide detail to show how T-bar ceilings supported by structure above.Provide water heater’s size. Is it sitting on the office ceiling? Provide complete support detail.