HomeMy WebLinkAbout254327_1_Corrections.docxTENANT IMPROVEMENT
PLAN CHECK COMMENTS
COMMENTS
Planning & Building Agency
Building Safety Division
20 Civic Center Plaza
P.O. Box 1988 (M-19)
Santa Ana, CA 92702
(714) 647-5800
www.santa-ana.org
PLAN CHECK NO:
101100269
PROJECT ADDRESS:
1904 W First St
PLAN CHECK ENGINEER:
Heidari, FredTEL:714
647-5862FAX:714
647-5897
TYPE OF CONSTRUCTION:
III B
OCCUPANCY CLASSIFICATION(S):
S-1
PLAN CHECK DATES:
REMARKS/RECHECK ITEMS:
APPLICATION
6/20/2019
INITIAL REVIEW
7/1/2019
EXPIRATION
12/17/2019
RECHECKS:
1.
PROJECT APPLICANT CONTACT PERSON:
2.
Andrea Munoz
3.
TEL:
(714)887-3053
FAX:
VALUATION:$60,000.00
EMAIL:
ammunoz1970@gmail.com
FLOOD ZONE:X-0602320257J
APPLICABLE CODE: 2016 CALIFORNIA BUILDING CODE (CBC) WITH
CITY OF SANTA ANA AMENDMENTS
All items noted on this plan check report must be addressed. If you feel that an item is not applicable to your project, note “N/A” and discuss the reason with the plan checker.Please indicate the sheet number and detail to the right of each correction, or note the number on the plans where the correction is made. Resubmit marked original, calculations and this correction sheet. A separate sheet for response may be used.Resubmit 3corrected sets of plans.Meetings between the project applicant/designer and the plan reviewer shall be by appointment only. Please call (714) 647-5862 for an appointment.The drawings/information submitted for Building Safety Division review is incomplete. The applicant shall, prior to resubmitting, complete all construction documents to show compliance with the 2016 California Building Standards Code with local amendments.Clearly indicate the scope of work under this building permit application:
- Revise project job description (Summary of work) on the cover sheet ( “G0.0”) to reflect the work to be done under the subject building permit application. All the: “G” sheets shall be removed from this drawings.
- Construction drawings must clearly show all work to be done under the subject building permit application.
- Delete all notes and details from drawings that are not a part of the work to be done under the subject building
permit application. This includes mechanical, plumbing and electrical work that is not specifically required by
the Building Code.All drawings and supporting documents shall be prepared, stamped and signed by a California licensed architect or registered civil engineer.Include address and telephone number of the responsible designer, and date of signing of drawings.This review does not include mechanical, plumbing, fire sprinkler system, or electrical work. Separate plans, applications, fees, plan checks, and permits are required for mechanical, plumbing, fire sprinkler systems, and electrical work. Call 647-5800 for information.The applicant shall obtain clearances/approvals for the following prior to building permit issuance:
- Planning Division approval on the corrected/final set of drawings (647-5804.) Previously approved plans
should be submitted to expedite the process.
- Orange County Fire Authority approval on the corrected/final sets of drawings ((714)573-6100)
- Police Department approval on the corrected/final set of drawings (647-5840)
- Public Works Agency approval (647-5039)
- Grading Permit. Application is made through the Building Safety Division (647-5800) and the plan review is by
the Public Works Agency (647-5039)
- School District Compliance Certificate; a copy of the building permit application, signed by the plan check
engineer, shall be required by the School District to verify the scope of work. Refer to the attached handout.
- Proof of Worker’s Compensation Insurance shall be required at the time of permit issuanceSubmit a signed copy of the contract showing labor and materials for all work to be done under the subject building permit application. The plan check engineer may accept the contract price as the valuation of improvements for unique/unusual projects in lieu of using a cost per square foot basis.The valuation of improvements for the subject building permit application has been calculated to be $300,000.00Provide pedestrian protection in accordance with CBC Section 3306. Show location and type of protection on plan view. Provide typical construction details, sections, and elevations of pedestrian protection required. Pedestrian protection constructed within a public right of way shall require a building permit issued by the Building Safety Division and a separate approval from the City’s Public Works Agency (714) 647-5039.Provide the following:
- Provide a fully dimensioned site plan on each set of plans.
- Disabled access compliance must be shown on the site plan.
- Show all property lines of record on the site plan.Show on the plans:
- Complete legal description
- Assessor’s Parcel Number
- Project Address/Suite/Room Numbers; Building Numbers
- Occupancy Classification(s)
- Type of Construction
- Fire Sprinkler System For the recheck, please provide a signed copy of the Soils Report for this site to support the soils allowable bearing and lateral pressure used in the design.
-