HomeMy WebLinkAbout255282_4_Corrections.docxTENANT IMPROVEMENT
PLAN CHECK COMMENTS
COMMENTS
Planning & Building Agency
Building Safety Division
20 Civic Center Plaza
P.O. Box 1988 (M-19)
Santa Ana, CA 92702
(714) 647-5800
www.santa-ana.org
PLAN CHECK NO:
101100548 & 101100549
PROJECT ADDRESS:
3220 & 3230 S Standard Ave
PLAN CHECK ENGINEER:
Heidari, FredTEL:714
647-5862FAX:714
647-5897
TYPE OF CONSTRUCTION:
V B
OCCUPANCY CLASSIFICATION(S):
B, S-1
PLAN CHECK DATES:
REMARKS/RECHECK ITEMS:
APPLICATION
6/24/2019
INITIAL REVIEW
7/3/2019
EXPIRATION
12/21/2019
RECHECKS:
1. 07/31/2019
PROJECT APPLICANT CONTACT PERSON:
2. 08/19/2019
Mary Artavia
3.
TEL:
(310)795-2506
FAX:
VALUATION:$375,000.00
EMAIL:
FLOOD ZONE:X-0602320278J
A recheck of your drawings was completed today, 08/19/2019; and the following items from the list below are not done/ completed at this time. See the list below for item # 6, 9.
For Item # 9, please obtain Orange County Fire Authority approval on the drawings.
Also, the structural sheets are not attached to these plans for recheck. Please provide/ add the structural sheet to these drawings.
The drawings are placed at the plan check counter.
A recheck of your drawings was completed today, 07/31/2019; and the following items from the first plan check are not done/ completed at this time. See the list below for item # 6, 9, 19, 20, 22, 27, & 32.
See more comments in the body of list below.
APPLICABLE CODE: 2016 CALIFORNIA BUILDING CODE (CBC) WITH
CITY OF SANTA ANA AMENDMENTS
All items noted on this plan check report must be addressed. If you feel that an item is not applicable to your project, note “N/A” and discuss the reason with the plan checker.Please indicate the sheet number and detail to the right of each correction, or note the number on the plans where the correction is made. Resubmit marked original, calculations and this correction sheet. A separate sheet for response may be used.Resubmit 2corrected sets of plans.Meetings between the project applicant/designer and the plan reviewer shall be by appointment only. Please call (714) 647-5862 for an appointment.This review does not include mechanical, plumbing, or electrical work. Separate plans, applications, fees, plan checks, and permits are required for mechanical, plumbing, and electrical work. Call 647-5800 for information.The applicant shall obtain clearances/approvals for the following prior to building permit issuance:This item is not done as of 07/31/2019.
- Planning Division approval on the corrected/final set of drawings (647-5804.) Previously approved plans
should be submitted to expedite the process.
- Public Works Agency approval (647-5039)
- Proof of Worker’s Compensation Insurance shall be required at the time of permit issuanceProvide the following:
- Provide a fully dimensioned site plan on each set of plans.
- Disabled access compliance must be shown on the site plan.City records note the type of building construction as VB under a previous/out-of-date code edition. Please note type of construction on drawing VBbased on the 2016 California Building Code Chapters 5 and 6.See red marks on sheet A0.00.Occupancies storing, handling, using, and/or selling hazardous materials, liquids, and chemicals shall submit a list of all said materials, listing their quantities and how they relate to specific California Building Code Table items. Note on the Floor Plan, type and quantity of hazardous material in each control area and fire-resistive rating for fire barriers.A table of “hazard waste” has been added to sheet “A1.02”. We need OCFA’s input for analyzing this table and to see if it’s below threshold for this building or not.Provide typical section view detail of all new partitions and ceilings showing:
- Size, spacing, and material of framing members
- Note gauge and ICC Research Report number and installation/construction requirements for metal framing
members.
- Method of attaching framing to the building structure. Do not support top of walls to suspended ceiling system unless calculations and drawing prepared by a registered engineer are submitted for review. Submit structural engineering calculations for walls in rooms with a floor to building structure above height greater than 14’.
- Heights of partition, suspended ceiling, structure above.Provide on the drawings interior wall and ceiling finish schedule showing compliance with CBC Section 803 and CBC Table 803.11.Note on drawing: “Exit doors shall be openable from the inside without the use of a key or any special knowledge or effort.”Hand-activated door opening hardware shall be centered between 34” and 44” above the floor. See red marks on sheet A0.01.Note on the drawings: “Maximum effort to operate doors shall not exceed 5 pounds for exterior doors and interior doors, such pull or push effort being applied at right angles to hinged doors and at the center place of sliding or folding doors. See red marks on sheet A0.01.The bottom 10” of all doors except automatic and sliding shall have a smooth uninterrupted surface to allow the door to be opened by a wheelchair footrest without creating a trap or hazardous condition.CBC Section 1008.2, Requires means of egress from all occupied parts of the building be provided with at least 1’ candle of light at floor level. Provide a note on the drawings.Tactile exit signs shall be required at the following locations:
- Each grade-level exterior exit door shall be identified by a tactile exit with the word “EXIT.”
- Each exit door that leads directly to a grade-level exterior exit by means of an exit enclosure, or an exit
passageway, shall be identified by a tactile exit sign with the words “EXIT ROUTE.”
- Each exit access door from an interior room or area to a corridor or hallway, which is required to have a visual
exit sign, shall be identified by a tactile exit sign with the words “EXIT ROUTE.”
- Each exit door through a horizontal exit shall be identified by a sign with the words “TO EXIT.”It is the project designer’s/property owner’s responsibility to show compliance on the drawings with all applicable Federal and State Accessibility Standards.Drawings submitted to the Building Division for review shall provide the following information to insure compliance with CBC Chapter 11B:
- An accessible entrance, Please provide a detail to show compliance with CBC.
- An accessible route to the altered area, Plans shall provide accessible route from the entry door to altered area.
- Accessible restrooms, Provide directional sign from existing restroom to the accessible unisex restroom.
- Accessible telephone (if any)
- Accessible drinking fountains, andis the drinking fountain accessible?
- Parking, signage and alarmsEntrance(s) to the building or facility and primary path of travel to the specific area of new work, alteration, structural repair or addition shall be accessible. Path of travel incorporated all elements from the exterior arrival site to remodeled area.This item is not done as of 07/31/2019.Sidewalks accommodating the disabled must be at least forty-eight inches (48”) wide and at least sixty inches (60”) where door swings over walk.Provide a continuous walking surface from each exit door to public way.Per site plan on sheet “A1.01”, there is a fence between these 2 buildings and the public way with a gate. Provide full compliance with chapters 10 and 11B for this gate to show that this gate complies with the exiting and accessibility requirements.Walks, sidewalks, and pedestrian ways shall be free of gratings whenever possible. For gratings located in the surface of any of these areas, grid openings in gratings shall be limited to ½” in the direction of traffic flow.If a walk crosses or adjoins a vehicular way, and the walking surfaces are not separated by curbs, railings or other elements between the pedestrian areas and vehicular areas, the boundary between the areas shall be defined by a continuous detectable warning which is 36” wide, complying with the CBC Section 11B-274.Accessible parking spaces serving a particular building shall be located on the shortest accessible route of travel from adjacent parking to an accessible entrance. Provide parking data on the site plan showing the total number of parking spaces provided, the number of disabled accessible spaces and the number of van accessible spaces, showing compliance with CBC Section 11B-208 and CBC Table 11B-208.2.CBC Section 11B-502.7.1. Parking spaces must be located so that the disabled are not compelled to walk or wheel behind parked cars other than their own.The proposed parking spaces for building at 3230 S. Standard Street do not comply with 11B-502.7.1.CBC Section 11B-208.2.4. One in every six accessible spaces, but not less than one, shall be served by an access aisle 8’-0” (96”) wide minimum and shall be designated van accessible.Provide completely dimensioned floor plans, elevations and sections of sanitary facility insuring wheelchair clearances complying with CBC Section 11B-604 and the California Plumbing Code.Note on the drawings hot water and drain pipes under lavatory shall be insulated.Ensure sanitary facilities comply with CBC Section 11B604 and that the bottom of the mirror is no higher than 40” from the floor.Show compliance with CBC Chapter 11B Section 11B-227.3 for the countersfor these two buildings.The detail 8/A5.01 does not show compliance with CBC chapter 11B.Show compliance with CBC Section 11B-228 & 11B-812 for any EV charging station.Show/note ventilation requirements on the plans in accordance with the CBC and California Mechanical Code (CMC) requirements for each type of use.
Note on drawings:
- All enclosed portions of buildings customarily occupied by human beings shall be provided with natural
ventilation by means of openable exterior openings readily controllable by building occupants, with an area not
less than 4% of the floor area being ventilated.
- Provide mechanical ventilation for each area/room in accordance with the 2016 California Mechanical Code.Provide structural calculations and drawings, stamped and signed by a California licensed architect or registered civil engineer for:
- New mechanical equipment on roof (note on Roof Framing Plan weight of each existing and new piece of
equipment on the roof)
- New equipment screening on roof
- Structural support of ceiling mounted monitors and fans
- Any other structural alteration