PLAN CHECK NO:
101101824
PROJECT ADDRESS:
511 E Goetz Ave
PLAN CHECK ENGINEER:
Heidari, FredTEL:714
647-5862
EMAIL:
fHeidari@santa-ana.orgFAX:714
647-5897
TYPE OF CONSTRUCTION:
V B, SPK
OCCUPANCY CLASSIFICATION(S):
B
PLAN CHECK DATES:
REMARKS/RECHECK ITEMS:
APPLICATION
10/14/2019
INITIAL REVIEW
10/22/2019
EXPIRATION
4/11/2020
RECHECKS:
1. 12/17/2019
PROJECT APPLICANT CONTACT PERSON:
2.
Jerry Minich
3.
TEL:
(714)632-8999
FAX:
VALUATION: $105,000.00
EMAIL:
cityvision@msn.com
FLOOD ZONE: X-0602320278J
A recheck of your drawing was completed this morning, 12/17/2019; and the following items from the first plan check are not done/ completed at this time. See the list below for item # 8c, 8d, 11, 12, 21, 22, & 26.
APPLICABLE CODE: 2016 CALIFORNIA BUILDING CODE (CBC) WITH
CITY OF SANTA ANA AMENDMENTS
All items noted on this plan check report must be addressed. If you feel that an item is not applicable to your project, note “N/A” and discuss the reason with the plan checker.Please indicate the sheet number and detail to the right of each correction, or note the number on the plans where the correction is made. Resubmit marked original, calculations and this correction sheet. A separate sheet for response may be used.Resubmit 3corrected sets of plans.Meetings between the project applicant/designer and the plan reviewer shall be by appointment only. Please call (714) 647-5862 for an appointment.The drawings/information submitted for Building Safety Division review is incomplete. The applicant shall, prior to resubmitting, complete all construction documents to show compliance with the 2016 California Building Standards Code with local amendments.The official records of City of Santa Ana do not show any building permit for the canopy. Can you please provide evidence that the canopy on the East side was permitted?Also, the City records do not show a chance of occupancy for this building from “B” to “S1”, “B”. Provide full code compliance on the drawings for the proposed change of occupancy including the floor area justification. (The original permit for this building was issued on 11-22-1978 as “B” occupancy building with total of 46,780 SF and required 3-60’ yards to be maintained). When there has been a change in use or occupancy classifications, drawings shall show compliance with the CBC requirements for the new classifications.Provide full structural calculation with proper notes and details for all the structural items to be done for this building permit including:Existing Canopy if it was no permitted,Proposed retaining walls for the truck dock,Proposed openings into concrete wall. Submitted calculation is not covering full vertical and lateral loads for these openings,For relocated light standard.Calculations must be presented in a clear, legible, and organized manner conducive for structural plan review. A table of contents must be provided and pages must be numbered for referencing purposes. Resubmit revised calculations showing compliance.This review does not include mechanical, plumbing, fire sprinkler system, or electrical work. Separate plans, applications, fees, plan checks, and permits are required for mechanical, plumbing, fire sprinkler systems, and electrical work. Call 647-5800 for information.The applicant shall obtain clearances/approvals for the following prior to building permit issuance:
- Planning Division approval on the corrected/final set of drawings (647-5804.) Previously approved plans
should be submitted to expedite the process.
- Orange County Fire Authority approval on the corrected/final sets of drawings ((714)573-6100)
- Police Department approval on the corrected/final set of drawings (647-5840)
- Public Works Agency approval (647-5039)
- Grading Permit. Application is made through the Building Safety Division (647-5800) and the plan review is by
the Public Works Agency (647-5039)
- Proof of Worker’s Compensation Insurance shall be required at the time of permit issuanceA separate Building Permit Application is required for:
- Each structure
- Block wall(s)
- Light standard(s)
- Site improvementsProvide the following:
- Provide a fully dimensioned site plan on each set of plans.
- Disabled access compliance must be shown on the site plan.Show on the plans:
- Occupancy Classification(s)
- Type of Construction
- Area tabulation justifying floor area(s) of building(s)
- Fire Sprinkler System (State purpose of sprinkler system,
- Number, width, and purpose (cite code section) of yards required
- Number and fire-resistive rating of all Fire walls
- Number of stories/mezzanines and building height in feetHand-activated door opening hardware shall be centered between 34” and 44” above the floor. Latching and locking doors that are hand activated and which are in a path of travel shall be operable with a single effort by lever-type hardware, by panic bars, push-pull activating bars, or other hardware designed to provide passage without requiring the ability to grasp the opening hardware. Locked exit doors shall operate as above in egress direction.Note on the drawings: “Maximum effort to operate doors shall not exceed 5 pounds for exterior doors and interior doors, such pull or push effort being applied at right angles to hinged doors and at the center place of sliding or folding doors. The bottom 10” of all doors except automatic and sliding shall have a smooth uninterrupted surface to allow the door to be opened by a wheelchair footrest without creating a trap or hazardous condition.It is the project designer’s/property owner’s responsibility to show compliance on the drawings with all applicable Federal and State Accessibility Standards.Drawings submitted to the Building Division for review shall provide the following information to insure compliance with CBC Section 11B-202:
- An accessible entrance
- An accessible route to the altered area
- Accessible restrooms
- Accessible telephone (if any)
- Accessible drinking fountains, and
- Parking, signage and alarmsValuation of proposed project is calculated as $ 105,000. A minimum of 20% of valuation of construction is required to be spent towards providing disabled access in the priority order noted in the immediate previous item as noted in CBC Section 11B202. Revise the drawings to show compliance. Show both existing elements and how they will be upgraded to current standards.Entrance(s) to the building or facility and primary path of travel to the specific area of new work, alteration, structural repair or addition shall be accessible. Path of travel incorporated all elements from the exterior arrival site to remodeled area.If a walk crosses or adjoins a vehicular way, and the walking surfaces are not separated by curbs, railings or other elements between the pedestrian areas and vehicular areas, the boundary between the areas shall be defined by a continuous detectable warning which is 36” wide, complying with the CBC Section 11B-247.Revise the drawings to show the words NO PARKING shall be painted on the ground within each loading and unloading access aisle. This notice shall be painted in white letters no less than 12” high and located so that it is visible to traffic enforcement officials. Sanitary facilities serving the area of new work shall be disabled accessible. Revise the drawings to show compliance with CBC Section11B-604.Provide completely dimensioned floor plans, elevations and sections of sanitary facility insuring wheelchair clearances complying with CBC Section 11B-604 and the California Plumbing Code.Note on the drawings hot water and drain pipes under lavatory shall be insulated.Drinking fountains serving the area of new work shall be accessible. CBC Section 11B-211.2 and California Plumbing Code.