HomeMy WebLinkAbout263722_1_Corrections.docxTENANT IMPROVEMENT
PLAN CHECK COMMENTS
COMMENTS
Planning & Building Agency
Building Safety Division
20 Civic Center Plaza
P.O. Box 1988 (M-19)
Santa Ana, CA 92702
(714) 647-5800
www.santa-ana.org
PLAN CHECK NO:
101103314
PROJECT ADDRESS:
1610 E First St
PLAN CHECK ENGINEER:
Ahangian, KathyTEL:714
647-5812
EMAIL:
Kahangian@santa-ana.orgFAX:714
647-5897
TYPE OF CONSTRUCTION:
N/A
OCCUPANCY CLASSIFICATION(S):
A-3
PLAN CHECK DATES:
REMARKS/RECHECK ITEMS:
APPLICATION
2/27/2020
INITIAL REVIEW
4/22/2020
EXPIRATION
8/25/2020
RECHECKS:
1.
PROJECT APPLICANT CONTACT PERSON:
2.
Alan El
3.
TEL:
(714)800-9039
FAX:
VALUATION: $25,000.00
EMAIL:
alanel@1stclassrl.com
FLOOD ZONE: X-0602320276J
APPLICABLE CODE: 2019 CALIFORNIA BUILDING CODE (CBC) WITH
CITY OF SANTA ANA AMENDMENTS
All items noted on this plan check report must be addressed. If you feel that an item is not applicable to your project, note “N/A” and discuss the reason with the plan checker.Please indicate the sheet number and detail to the right of each correction, or note the number on the plans where the correction is made. Resubmit marked original, calculations and this correction sheet. A separate sheet for response may be used.Resubmit 2corrected sets of plans.Meetings between the project applicant/designer and the plan reviewer shall be by appointment only. Please call (714) 647-5812 for an appointment.Please return marked up set of drawings with corrections.The applicant shall obtain clearances/approvals for the following prior to building permit issuance:
- Planning Division approval on the corrected/final set of drawings (647-5804.) Previously approved plans
should be submitted to expedite the process.
- Fire Department approval on the corrected/final sets of drawings ((714)573-6100)
- Proof of Worker’s Compensation Insurance shall be required at the time of permit issuanceAll doors require a level floor landing on each side in accordance with CBC Sections 1010.1.5 Provide typical door threshold details and details of change in floor covering material.Landing cannot be on the side walk and door cannot swing over the side walk, door needs to be recessed.CBC Sections 11B-303 Regardless of the occupant load, there shall be a floor or landing on each side of a door. The floor or landing shall be not more than ½” lower than the threshold of the doorway. Change in level between ¼” and ½” shall be beveled with a slope no greater than 1:2. Change in level greater than ½” shall be accomplished by means of a ramp. Provide detailed sections and plan views showing compliance at all doorways requiring accessibility.CBC Section 11404.2.9Note on the drawings: “Maximum effort to operate doors shall not exceed 5 pounds for exterior doors and interior doors, such pull or push effort being applied at right angles to hinged doors and at the center place of sliding or folding doors. Compensating devices or automatic door operators may be utilized to meet the above standards. When fire doors are required, the maximum effort to operate the door may be increased to the minimum allowable by the appropriate administrative authority, not to exceed 15 pounds.CBC Section 11B404.2.10, Required the bottom 10” of all doors except automatic and sliding shall have a smooth uninterrupted surface to allow the door to be opened by a wheelchair footrest without creating a trap or hazardous condition.Provide minimum 24” clearance to the strike edge of the gate.Panic hardware does not work for double swing gate.