HomeMy WebLinkAbout264792_2_Corrections.docxRESIDENTIAL PLAN CHECK COMMENTS Planning & Building Agency Building Safety Division 20 Civic Center Plaza P.O. Box 1988 (M-19) Santa Ana, CA 92702 (714) 647-5800 www.santa-ana.org PLAN CHECK NO: 101103601 PROJECT ADDRESS: 2221 1/2 S Cypress Ave PLAN CHECK ENGINEER: Ahangian, KathyTEL:714 647-5812 EMAIL: Kahangian@santa-ana.orgFAX:714 647-5897 TYPE OF CONSTRUCTION: V B OCCUPANCY CLASSIFICATION(S): R-3 PLAN CHECK DATES: REMARKS/RECHECK ITEMS: APPLICATION 5/21/2020 INITIAL REVIEW 6/1/2020 EXPIRATION 11/17/2020 RECHECKS: 1. PROJECT APPLICANT CONTACT PERSON: 2. Minh Trung Tran 3. TEL: (714)875-2408 FAX: VALUATION: $80,000.00 EMAIL: mtranoc@gmail.com FLOOD ZONE: X-0602320278J Note: Numbers in parenthesis (unless otherwise noted) refer to code sections of the 2019 California Residential Code (CRC); 2019 California Building Code (CBC); CMC = 2019 California Mechanical Code; CPC = 2019 California Plumbing Code; CEC = 2019 California Electrical Code; T = Table; ICC = International Code Council.All items noted on this plan check report must be addressed. If you feel that an item is not applicable to your project, note “N/A” and discuss the reason with the plan checker.Please indicate the sheet number and detail to the right of each correction, or note the number on the plans where the correction is made. Resubmit marked original, calculations and this correction sheet. A separate sheet for response may be used.Resubmit 3corrected sets of plans.Meetings between the project applicant/designer and the plan reviewer shall be by appointment only. Please call (714) 647-5812 for an appointment.The drawings/information submitted for Building Safety Division review is incomplete. The applicant shall, prior to resubmitting, complete all construction documents to show compliance with the 2019California Building Standards Code with local amendments and to clearly indicate the scope of work under this building permit application. There may be additional requirements when complete construction drawings and supporting data is submitted for Building Safety Division review. Please see corrections on submitted plans. Red marked set must be returned with revised plans. Plans resubmitted without the red markup set may result in delayed review time and additional plancheck fees. All drawings and supporting documents shall be prepared, stamped, and signed by a California licensed architect or registered professional engineer. (CRC R301.1.3, CBC 107.1 and 107.3.4.1).All persons preparing plans for others shall sign those plans. Business and Professions Code Chapter 3, Division 3, Section 5536.1 (a). This review does not include mechanical, plumbing or electrical work. Separate plans, applications, fees, plan checks, and permits are required for mechanical, plumbing, and electrical work. Call 647-5800 for information. The applicant shall obtain clearances/approvals for the following, prior to building permit issuance: -Planning Division approval on the corrected/final set of drawings (647-5804). Previously approved plans should be submitted to expedite the process. -Police Department approval on the corrected/final set of drawings (647-5840). -Public Works Agency approval (647-5039). - Proof of Worker's Compensation Insurance shall be required at the time of permit issuance. - School District Compliance Certificate; and a copy of the building permit application, signed by the plan check engineer, shall be required by the School District to verify the scope of the work. - Grading Permit. Application is made through the Building Safety Division (647-5800) and theplan review is by the Public Works Agency (647-5039).In addition to other fees, a "Park Acquisition and Development Fee" in the amount shownbelow shall be required pursuant to a resolution of the City Council for the Recreation andCommunity Services Agency; net addition of ________ bedroom(s).Amount of $4,612.67; net addition of 2 bedrooms Provide a fully dimensioned Site Plan on the drawings and on a separate 8-1/2" x 11" sheet of paper. Provide a statement on the title sheet of the plans that this project shall comply with following codes: - 2019 California Residential Code (CRC) - 2019 California Building Code (CBC) - 2019 California Electrical Code (CEC) - 2019 California Mechanical Code (CMC) - 2019 California Plumbing Code (CPC) - 2019 California Green Building Standards Code (CGBS) or CALGreen - 2019 California Energy Code (CEnC) - City of Santa Ana Municipal Code Lots shall be graded to drain surface water away from foundation walls. The grade shall fall a minimum of 6 inches within the first 10 feet. (CRC R401.3) Indicate detail and section references as to their appropriate location on the plan view.Basements, habitable attics, and every sleeping room in dwelling units must have a window or exterior door for an emergency exit, sill height not more than 44 inches above the floor, 5.7 square feet of openable area, 24 inches clear opening height, 20 inches clear opening width and shall open directly into a public street, alley, yard, or exit court. Windows ______ do not comply. (CRC R310.1-R310.1.3) (For both bedrooms)Show 30-inch clear width for water closet compartments and 24-inch clearance in front of a water closet. Glass enclosure doors and panels must be labeled Category II. Swing door outward. Net area of shower receptor shall be not less than 1,024 sq. in. of floor area, and encompass 30-inch diameter circle. (CPC411.7)Glazing in swinging, sliding, and bifold doors 9 square feet or less shall be a minimum category classification of I (CPSC 16 CFR 1201) and II (CPSC 16 CFR 1201) when more than 9 square feet or sliding. (Table R308.3.1 (1), R308.3 (1)) Show exterior wall construction assembly. A minimum of one layer of No. 15 asphalt felt, free from holes and breaks, complying with ASTM D 226 for Type 1 felt shall be applied over studs of all exterior walls. Specify that two layers of Grade D or 60 minute Grade D paper shall be applied over all wood base sheathing. (CRC R703.2) Post-beam connections must be detailed on the drawings ensuring against uplift and lateral displacement ( For all beams) Detail the shear transfer connections which transfer lateral forces from horizontal diaphragms through intermediate elements and shear walls to the foundation. (1603) The City has encountered a large number of inspection problems arising from a lack of specific framing details. The following listed items are required to be shown on the plans (CBC 107.1): - All plumbing walls are to be framed with a minimum of 6" studs. - Permissible notching and boring of joists are to be shown on the plans and shall not exceed CBC Section 2308.10.4.2 allowances. - Notching of exterior and bearing/nonbearing walls shall not exceed 25%/40% respectively. Bored holes in bearing/nonbearing walls shall not exceed 40%/60% respectively. In no case shall the edge of the bored hole be nearer than 5/8 inch to the edge of the stud. (2308.9.10 and 2308.9.11) - Header and trimmer details for doors and windows are to be shown with full length trimmers, specifying the size of the header and trimmer. Call out anchor bolt size and spacing on foundation plan. Provide 1/2" diameter embedded 7" minimum at 6' o.c. maximum spacing (4' o.c. for 2 stories). On the drawings add the notes from Geotechnical report for site preparation. Add all necessary Inspection from soils report on the drawings from page 12. Provide detail for ceiling joists splice. Provide dimension and show exact location of beam #3 over beam #4.The residence shall conform to the State Energy Conservation Standards. Submit forms and calculations for review and blueprint the final forms on the plans. - Also, submit 2 copies of signed Energy Efficiency calculations. -The energy plan check consultant must sign documentation forms on behalf of the Building Safety Division. - The energy plan check consultant must also complete the attached “Energy Conservation Plan Check Consultant Qualification Statement”.Please fillout attached Green building code forms and copy them on the drawings.Provide anchorage details for FAU units. (CMC 303.4) Identify all the items on the roof plan.