HomeMy WebLinkAbout267291_1_Corrections.docxRESIDENTIAL PLAN CHECK COMMENTS Planning & Building Agency Building Safety Division 20 Civic Center Plaza P.O. Box 1988 (M-19) Santa Ana, CA 92702 (714) 647-5800 www.santa-ana.org PLAN CHECK NO: 101104275 PROJECT ADDRESS: 502 S Cooper St PLAN CHECK ENGINEER: Le, TungTEL:714 647-5896 EMAIL: Tle10@santa-ana.orgFAX:714 647-5897 TYPE OF CONSTRUCTION: V B OCCUPANCY CLASSIFICATION(S): R-3, U PLAN CHECK DATES: REMARKS/RECHECK ITEMS: APPLICATION 8/12/2020 INITIAL REVIEW 10/6/2020 EXPIRATION 2/8/2021 RECHECKS: 1. PROJECT APPLICANT CONTACT PERSON: 2. Michael Luna 3. TEL: (951)685-4418 FAX: VALUATION: $12,000.00 EMAIL: Manuelunafelix@hotmail.com FLOOD ZONE: A-0602320252J Note: Numbers in parenthesis (unless otherwise noted) refer to code sections of the 2019 California Residential Code (CRC); 2019 California Building Code (CBC); CMC = 2019 California Mechanical Code; CPC = 2019 California Plumbing Code; CEC = 2019 California Electrical Code; T = Table; ICC = International Code Council.All items noted on this plan check report must be addressed. If you feel that an item is not applicable to your project, note “N/A” and discuss the reason with the plan checker.Please indicate the sheet number and detail to the right of each correction, or note the number on the plans where the correction is made. Resubmit marked original, calculations and this correction sheet. A separate sheet for response may be used.Resubmit 2corrected sets of plans. The applicant shall obtain clearances/approvals for the following, prior to building permit issuance: -Planning Division approval on the corrected/final set of drawings (647-5804). Previously approved plans should be submitted to expedite the process. Sheet A1: Please indicate on plan the pool is under a separate permit. Sheet A1, Site plan: It’s not an enclosed patio. Please remove note indicate “Enclosure”. Sheet A1, Building Summary: Plan must be legible. Please increase font size and contrast. Sheet A1, Scope of Work: Please revise scope of work to exclude the new swimming pool. Sheet A2: Please specify (N) Pool is under a separate permit. Sheet A2: Please show distance setback between new patio wall and property line. Sheet A2: The building cross-section callout were mislabeled. Please coordinate and revise plan accordingly. Sheet A2: BBQ shall not locate under a combustible construction (patio cover). Sheet A3: On the plan, please specify roofing material and underlayment. Sheet A3: On the plan, please provide/show roof drain and overflow at the new flat roof. Show location and provide details. Section B-B/S-2: Please clearly ceiling finish material. Portal wall: On the plan, please specify ICC listing number. Provide complete Simpson portal spec sheets on the plan. Cantilever steel beam to steel column welding calculation: Please revise calculation include the moment due to the concentrated load at the end of the cantilever beam.