HomeMy WebLinkAbout267547_2_Corrections.docxTENANT IMPROVEMENT
PLAN CHECK COMMENTS
COMMENTS
Planning & Building Agency
Building Safety Division
20 Civic Center Plaza
P.O. Box 1988 (M-19)
Santa Ana, CA 92702
(714) 647-5800
www.santa-ana.org
PLAN CHECK NO:
101104337
PROJECT ADDRESS:
515 E Dyer Rd
PLAN CHECK ENGINEER:
Le, TungTEL:714
647-5896
EMAIL:
Tle10@santa-ana.orgFAX:714
647-5897
TYPE OF CONSTRUCTION:
V B, SPK
OCCUPANCY CLASSIFICATION(S):
U, B, S-1, S-2
PLAN CHECK DATES:
REMARKS/RECHECK ITEMS:
APPLICATION
8/20/2020
Screen wall and gates
INITIAL REVIEW
9/8/2020
EXPIRATION
2/16/2021
RECHECKS:
1.
PROJECT APPLICANT CONTACT PERSON:
2.
Doug Hinrichs
3.
TEL:
(949)862-2135
FAX:
VALUATION: $100,000.00
EMAIL:
doug.hinrichs@hparchs.com
FLOOD ZONE: X-0602320278J
APPLICABLE CODE: 2019 CALIFORNIA BUILDING CODE (CBC) WITH
CITY OF SANTA ANA AMENDMENTS
General / Approval
All items noted on this plan check report must be addressed. If you feel that an item is not applicable to your project, note “N/A” and discuss the reason with the plan checker.Please indicate the sheet number and detail to the right of each correction, or note the number on the plans where the correction is made. Resubmit marked original, calculations and this correction sheet. A separate sheet for response may be used.Resubmit 2corrected sets of plans.The applicant shall obtain clearances/approvals for the following prior to building permit issuance:
- Planning Division approval on the corrected/final set of drawings (647-5804.) Previously approved plans
should be submitted to expedite the process.
- Fire Department approval on the corrected/final sets of drawings ((714)573-6100)
- Police Department approval on the corrected/final set of drawings (647-5840)
- Public Works Agency approval (647-5039)Sheet TI-A0.1:CMU screen wall: On the plan, please specify the linear feet and maximum height of the proposed screen walls. Code Analysis: Please update occupant load calculation accordingly. Refer to T.I. plan check comments. Project Data: Please update parking count accordingly. Refer to T.I. plan check comments. Sheet TI-A1.1:On the plan, please show streets. On the plan, please clearly identify existing vs. proposed walls. All required exits shall be continuous to a public way in accordance with Section 1009.2. Please show a continuous path of travel to public way from the required exits. Pedestrian gates may be required. Please coordinate with T.I plans. Sheet TI-A3.3: On the plan, please show wall and column height. Sheet S5.1:For clarity, please identify existing vs. new wall, including property line wall. Structural Review CommentStructural calculation: Soil Data – Please provide soil reports to verify the soil parameters. Per structural calculation, the CMU stem walls are not located at centerline of footing. Please coordinate toes width and heel width with details provided on sheet S-5.2. Structural calculation: Lateral force applied to stem wall – Should it be 37.0 psf? The 23.1 psf appeared understated – Please see Design Loads on page 12. Please revise and plan accordingly.