HomeMy WebLinkAbout269935_3_Corrections.docxTENANT IMPROVEMENT
PLAN CHECK COMMENTS
COMMENTS
Planning & Building Agency
Building Safety Division
20 Civic Center Plaza
P.O. Box 1988 (M-19)
Santa Ana, CA 92702
(714) 647-5800
www.santa-ana.org
PLAN CHECK NO:
101105138
PROJECT ADDRESS:
3350 S Bristol St Unit# B
PLAN CHECK ENGINEER:
So, AnsonTEL:714
647-5830
EMAIL:
aso@santa-ana.orgFAX:714
647-5897
TYPE OF CONSTRUCTION:
V B, SPK
OCCUPANCY CLASSIFICATION(S):
B
PLAN CHECK DATES:
REMARKS/RECHECK ITEMS:
APPLICATION
11/4/2020
INITIAL REVIEW
11/19/2020
EXPIRATION
5/3/2021
RECHECKS:
1.
PROJECT APPLICANT CONTACT PERSON:
2.
Vicky Li
3.
TEL:
(714)906-5714
FAX:
(888)473-9995
VALUATION: $20,000.00
EMAIL:
vickyli8875@yahoo.com
FLOOD ZONE: X-0602320259J
APPLICABLE CODE: 2019 CALIFORNIA BUILDING CODE (CBC) WITH
CITY OF SANTA ANA AMENDMENTS
All items noted on this plan check report must be addressed. If you feel that an item is not applicable to your project, note “N/A” and discuss the reason with the plan checker.Please indicate the sheet number and detail to the right of each correction, or note the number on the plans where the correction is made. Resubmit marked original, calculations and this correction sheet. A separate sheet for response may be used.Resubmit 2corrected sets of plans.Meetings between the project applicant/designer and the plan reviewer shall be by appointment only. Please call (714) 647-5830 for an appointment.Please return marked up set of drawings with corrections.Sheet T-1Revise the project address to 3350 S. Bristol St., Suite B,Santa Ana, CA 92704.Under Code Information, the plan shows the building does not have a fire sprinkler. However, according to City record, this is a sprinklered building. Verify if a sprinkler system is installed in this building.First Plan Check Comments: Revise the sheet number and titles on drawing index. The plumbing sheets and electrical sheets are not included in this plan set.Second Plan Check Comments: Remove plumbing and electrical sheets on the index and the set of plans.Sheet A-3A bench is shown in the waiting area. Provide accessible requirements per CBC Section 11B-903 on the plan.Correct the cross-referenced-detail number on the restroom.First Plan Check Comments:The plumbing fixture locations does not match detail 2/D-2. Correct the floor plan or revise all the elevation drawings on sheet D-2 as necessary.Second Plan Check Comments: The elevation drawing on the most left-hand side on detail one does not match the restroom plan view.