PLAN CHECK NO:
101104849
PROJECT ADDRESS:
4714 1/2 W Floyd Cir
PLAN CHECK ENGINEER:
Le, TungTEL:714
647-5896
EMAIL:
Tle10@santa-ana.orgFAX:714
647-5897
TYPE OF CONSTRUCTION:
V B
OCCUPANCY CLASSIFICATION(S):
R-3, U
PLAN CHECK DATES:
REMARKS/RECHECK ITEMS:
APPLICATION
10/5/2020
INITIAL REVIEW
11/3/2020
EXPIRATION
4/3/2021
RECHECKS:
1.1/6/2021
PROJECT APPLICANT CONTACT PERSON:
2.
Albert Luu
3.
TEL:
(714)858-5959
FAX:
VALUATION: $100,000.00
EMAIL:
albert.luu@hotmail.com
FLOOD ZONE: A-0602320256J
Note: Numbers in parenthesis (unless otherwise noted) refer to code sections of the 2019 California Residential Code (CRC); 2019 California Building Code (CBC); CMC = 2019 California Mechanical Code; CPC = 2019 California Plumbing Code; CEC = 2019 California Electrical Code; T = Table; ICC = International Code Council.General and approval requirement:All items noted on this plan check report must be addressed. If you feel that an item is not applicable to your project, note “N/A” and discuss the reason with the plan checker.Please indicate the sheet number and detail to the right of each correction, or note the number on the plans where the correction is made. Resubmit marked original, calculations and this correction sheet. A separate sheet for response may be used.Resubmit 3corrected sets of plans.
The applicant shall obtain clearances/approvals for the following, prior to building permit issuance:
-Planning Division approval on the corrected/final set of drawings (647-5804). Previously
approved plans should be submitted to expedite the process.
-Police Department approval on the corrected/final set of drawings (647-5840).
-Public Works Agency approval (647-5039).
- School District Compliance Certificate; and a copy of the building permit application, signed by
the plan check engineer, shall be required by the School District to verify the scope of the work.
-Grading Permit. Application is made through the Building Safety Division (647-5800) and the
plan review is by the Public Works Agency (647-5039).
This project is in a special flood hazard area designated on the flood insurance rate map (FIRM) as zone A. This zone requires that the lowest finish floor elevation (including basement) of the structure shall be at (or above) base flood elevation determined by a hydrology study for the A zone. All elevations must be referenced to the National Geodetic Vertical Datum. Reference should be made to the Flood Plain Management Ordinance, Santa Ana Municipal Code, Chapter 7, for complete requirements. Drawings shall show compliance with said ordinance including noting flood zone and finish floor elevation.
Note on plans: "A Federal Emergency Management Agency National Flood Insurance Program ELEVATION CERTIFICATE shall be completed by a California Licensed Land Surveyor or California Registered Civil Engineer who is authorized to practice land surveying. The completed ELEVATION CERTIFICATE must be submitted to the Building Inspector at the time of foundation inspection, and a final certificate must be submitted at the time of final inspection."
2nd Review Comment: Please provide the Elevation Certificate. The complete Elevation Certificate must be imprinted onto the plan.
The Hydrology and Hydraulic report was incomplete/insufficient for determining the base flood elevation (BFE). Zone A floodplains are those areas have not determined Base Flood Elevation (BFE). Below are some useful information provided on Official Vermont Government Website for your use. (Copied from the website: https://floodtraining.vermont.gov/protection-tools/zone-a)
2nd Review Comment: The Obtaining and Developing Base Flood Elevations in Zone A Area report by Ly Phan, P.E. – Under statement #4, please clarify bottom elevation of the channel at 54.5-ft vs. 48.71-ft showed on the channel’s cross section. Please coordinate and revise accordingly.