PLAN CHECK NO:
101105845
PROJECT ADDRESS:
2526 1/2 N Valencia St
PLAN CHECK ENGINEER:
Ahangian, KathyTEL:714
647-5812
EMAIL:
Kahangian@santa-ana.orgFAX:714
647-5897
TYPE OF CONSTRUCTION:
V B
OCCUPANCY CLASSIFICATION(S):
R-3
PLAN CHECK DATES:
REMARKS/RECHECK ITEMS:
APPLICATION
2/8/2021
INITIAL REVIEW
3/10/2021
EXPIRATION
8/7/2021
RECHECKS:
1.
PROJECT APPLICANT CONTACT PERSON:
2.
Scott Grady
3.
TEL:
(964)500-6192
FAX:
VALUATION: $150,000.00
EMAIL:
scottastongrady@yahoo.com
FLOOD ZONE: X-0602320163J
Note: Numbers in parenthesis (unless otherwise noted) refer to code sections of the 2019 California Residential Code (CRC); 2019 California Building Code (CBC); CMC = 2019 California Mechanical Code; CPC = 2019 California Plumbing Code; CEC = 2019 California Electrical Code; T = Table; ICC = International Code Council.All items noted on this plan check report must be addressed. If you feel that an item is not applicable to your project, note “N/A” and discuss the reason with the plan checker.Please indicate the sheet number and detail to the right of each correction, or note the number on the plans where the correction is made. Resubmit marked original, calculations and this correction sheet. A separate sheet for response may be used.Resubmit 3corrected sets of plans.Meetings between the project applicant/designer and the plan reviewer shall be by appointment only. Please call (714) 647-5812 for an appointment.
Please see corrections on submitted plans. Red marked set must be returned with revised plans. Plans resubmitted without the red markup set may result in delayed review time and additional plancheck fees.
All drawings and supporting documents shall be prepared, stamped, and signed by a California licensed architect or registered professional engineer. (CRC R301.1.3, CBC 107.1 and 107.3.4.1).
This review does not include mechanical, plumbing or electrical work. Separate plans, applications, fees, plan checks, and permits are required for mechanical, plumbing, and electrical work. Call 647-5800 for information.
The applicant shall obtain clearances/approvals for the following, prior to building permit issuance:
-Planning Division approval on the corrected/final set of drawings (647-5804). Previously
approved plans should be submitted to expedite the process.
- Fire Department approval on the corrected/final set of drawings (647-5839 or 647-5700).Please make an appointment with Johnathan Hobbs.
-Police Department approval on the corrected/final set of drawings (647-5840).
-Public Works Agency approval (647-5039).
- Proof of Worker's Compensation Insurance shall be required at the time of permit issuance.
- School District Compliance Certificate; and a copy of the building permit application, signed by
the plan check engineer, shall be required by the School District to verify the scope of the work.In addition to other fees, a "Park Acquisition and Development Fee" in the amount shownbelow
shall be required pursuant to a resolution of the City Council for the Recreation andCommunity
Services Agency; net addition of _3 bedroom(s).Amount of $6,415.00; net addition of 3 bedrooms
Provide a fully dimensioned Site Plan on the drawings and on a separate 8-1/2" x 11" sheet of paper.
Provide eave / overhang / projection setback to all property lines.Projections of dwelling units and accessory buildings without an automatic residential fire sprinkler protection are not permitted less than 2 feet to the property line and are required to be 1 hour fire rated on the underside with a fire separation distance between 2 feet and 5 feet. (CRC Table R302.1 (1)) Show location of heating equipment on the plans. (CRC R303.8)Revise plans to indicate that a landing, with a width not less than the width of door and length in the direction of travel of not less than 36 inches, will be provided on each side of doors. The elevation of landing shall not exceed 1 ½ inch difference than the threshold of the doorway (7 3/4 inch if door does not swing over the landing or steps) in each direction.Glazing in door and enclosures for hot tubs, whirlpools, saunas, steam rooms, bathrooms, showers less than 5’ above the standing surface shall have a minimum category classification of II (CPSC 16 CFR 1201). (CRC TR308.3.1 (1) & 308.4(5)) Callout attic vent locations, sizes and types on plans. Provide attic ventilation calculation to show minimum ventilation is provided. (CRC R806.2)Please copy grading permit exemption checklist on the drawings.Site drainage plan shall be stamped by engineer of record per grading check list.
The geotechnical report requires foundation excavations to be reviewed by a geotechnical engineer. Note on the foundation plan "Prior to requesting a Building Safety Division foundation inspection, the geotechnical engineer shall inspect and approve the foundation excavations." (1803)
Have the consulting geotechnical engineer review and approve the foundation plans. (1803)
Please add notes for footing and slab area preparation from soils report.
Unable to find concrete strength , cement type for concrete design on soils report.
The City has encountered a large number of inspection problems arising from a lack of specific framing details. The following listed items are required to be shown on the plans (CBC 107.1):
- All plumbing walls are to be framed with a minimum of 6" studs.
- Permissible notching and boring of joists are to be shown on the plans and shall not exceed CBC
Section 2308.10.4.2 allowances.
- Notching of exterior and bearing/nonbearing walls shall not exceed 25%/40% respectively. Bored
holes in bearing/nonbearing walls shall not exceed 40%/60% respectively. In no case shall the
edge of the bored hole be nearer than 5/8 inch to the edge of the stud. (2308.9.10 and 2308.9.11)
- Header and trimmer details for doors and windows are to be shown with full length trimmers,
specifying the size of the header and trimmer. (2308.10.4.3)Indicate all compliance measures from the energy compliance documentation on the plans. (i.e., Insulation for sections, U-factors SHGC). Revise door and window schedule or floor plans to show compliance. (T24-1-10.111)Insulation shown on the plans does not agree with CF-1R form; revise framing plans. Ceiling R = 38Detail 2/S3.1 doesn’t apply to the hip beam, please revise it.Detail 11/ S3.0 referenced on sheet S1.0 is not included.Provide detail for Hip beam/ ridge beam connection.Provide detail for the hip beam to the corners to prevent slipping off.Make a note “Solar panel permit shall be obtained and installed before final inspection.Please fillout attached residential green building forms and copy it on the drawings.