PLAN CHECK NO:
101105527
PROJECT ADDRESS:
901 W Civic Center Dr Unit# 190
PLAN CHECK ENGINEER:
Ahangian, KathyTEL:714
647-5812
EMAIL:
Kahangian@santa-ana.orgFAX:714
647-5897
TYPE OF CONSTRUCTION:
II A, SPK
OCCUPANCY CLASSIFICATION(S):
B
PLAN CHECK DATES:
REMARKS/RECHECK ITEMS:
APPLICATION
12/22/2020
INITIAL REVIEW
1/10/2021
EXPIRATION
6/20/2021
RECHECKS:
1.
PROJECT APPLICANT CONTACT PERSON:
2.
Sean Nourani
3.
TEL:
(424)365-2070
FAX:
VALUATION: $10,000.00
EMAIL:
architectseannourani@outlook.com
FLOOD ZONE: X-0602320144J
APPLICABLE CODE: 2019 CALIFORNIA BUILDING CODE (CBC) WITH
CITY OF SANTA ANA AMENDMENTS
All items noted on this plan check report must be addressed. If you feel that an item is not applicable to your project, note “N/A” and discuss the reason with the plan checker.Please indicate the sheet number and detail to the right of each correction, or note the number on the plans where the correction is made. Resubmit marked original, calculations and this correction sheet. A separate sheet for response may be used.Resubmit 2corrected sets of plans.Meetings between the project applicant/designer and the plan reviewer shall be by appointment only. Please call (714) 647-5812 for an appointment.Please return marked up set of drawings with corrections.CBC Sections A106.1 and A106.3.4.1, All drawings and supporting documents shall be prepared, stamped and signed by a California licensed architect or registered civil engineer.This review does not include mechanical, plumbing, fire sprinkler system, or electrical work. Separate plans, applications, fees, plan checks, and permits are required for mechanical, plumbing, fire sprinkler systems, and electrical work. Call 647-5800 for information.The applicant shall obtain clearances/approvals for the following prior to building permit issuance:
- Planning Division approval on the corrected/final set of drawings (647-5804.) Previously approved plans
should be submitted to expedite the process.
- Public Works Agency approval (647-5039)
- Proof of Worker’s Compensation Insurance shall be required at the time of permit issuanceLabel and note hourly fire rating of:
- All corridors
- Fire walls
- Fire barriersCBC Section 1022.1 Exit continuity. Exits shall be continuous from the point of entry into the exit to the exit discharge.CBC Sections 1002 and 1028.5EXIT DISCHARGE. That portion of a means of egress system between the termination of an exit and a public way.Provide on the drawings a complete door schedule, showing:
- Door sizes (CBC Sections 11B-404)
- Hardware complying with exiting and disabled accessibility requirements (CBC Sections 1008.1.8 and
1133B.2.5)
- Fire-rating of door assembly complying with CBC Section 715 Opening ProtectionTactile exit signs shall be required at the following locations:
- Each grade-level exterior exit door shall be identified by a tactile exit with the word “EXIT.”
- Each exit door that leads directly to a grade-level exterior exit by means of a stairway or ramp shall be
identified by a tactile exit sign with the following words as appropriate:
- Each exit door that leads directly to a grade-level exterior exit by means of an exit enclosure, or an exit
passageway, shall be identified by a tactile exit sign with the words “EXIT ROUTE.”
- Each exit access door from an interior room or area to a corridor or hallway, which is required to have a visual
exit sign, shall be identified by a tactile exit sign with the words “EXIT ROUTE.”
- Each exit door through a horizontal exit shall be identified by a sign with the words “TO EXIT.”Drawings submitted to the Building Division for review shall provide the following information to insure compliance with CBC Section 11B-202.4:
- An accessible entrance
- An accessible route to the altered area
- Accessible restrooms
- Accessible telephone (if any)
- Accessible drinking fountains, and
- Parking, signage and alarmsProvide a continuous walking surface from each exit door to public way.CBC Section 11B-502.3.4 Revise the drawings to show disabled accessible parking space loading/unloading aisle on the PASSENGER SIDE.Complete the attached Disabled Accessibility Documentation Form.