HomeMy WebLinkAbout270739_2_Corrections.docxRESIDENTIAL PLAN CHECK
COMMENTS
Planning & Building Agency
Building Safety Division
20 Civic Center Plaza
P.O. Box 1988 (M-19)
Santa Ana, CA 92702
(714) 647-5800
www.santa-ana.org
PLAN CHECK NO:
101105414
PROJECT ADDRESS:
1220 1/2 W Second St
PLAN CHECK ENGINEER:
Le, TungTEL:714
647-5896
EMAIL:
Tle10@santa-ana.orgFAX:714
647-5897
TYPE OF CONSTRUCTION:
V B
OCCUPANCY CLASSIFICATION(S):
R-3
PLAN CHECK DATES:
REMARKS/RECHECK ITEMS:
APPLICATION
1/25/2021
INITIAL REVIEW
2/24/2021
EXPIRATION
7/24/2021
RECHECKS:
1.4/29/2021
PROJECT APPLICANT CONTACT PERSON:
2.
Rubens Calderon
3.
TEL:
(714)803-4250
FAX:
VALUATION: $15,000.00
EMAIL:
rubenscalderon@gmail.com
FLOOD ZONE: X-0602320257J
Note: Numbers in parenthesis (unless otherwise noted) refer to code sections of the 2019 California Residential Code (CRC); 2019 California Building Code (CBC); CMC = 2019 California Mechanical Code; CPC = 2019 California Plumbing Code; CEC = 2019 California Electrical Code; T = Table; ICC = International Code Council.All items noted on this plan check report must be addressed. If you feel that an item is not applicable to your project, note “N/A” and discuss the reason with the plan checker.Please indicate the sheet number and detail to the right of each correction, or note the number on the plans where the correction is made. Resubmit marked original, calculations and this correction sheet. A separate sheet for response may be used.Resubmit 3corrected sets of plans.
The applicant shall obtain clearances/approvals for the following, prior to building permit issuance:
-Planning Division approval on the corrected/final set of drawings (647-5804). Previously
approved plans should be submitted to expedite the process.
-Police Department approval on the corrected/final set of drawings (647-5840).
-Public Works Agency approval (647-5039).
- School District Compliance Certificate; and a copy of the building permit application, signed by
the plan check engineer, shall be required by the School District to verify the scope of the work.
Sheet A-1:
Exterior walls locate less than 5-ft from the property line shall be protected with one-hour fire-rated construction. Please show fire-rated wall and provide construction details. Details shall clearly cross-reference onto the plan.
2nd Review Comment: Response was incomplete. Please provide detail to show one-hour rated wall assembly. Detail shall be clearly cross-referenced onto the plan.
Sheet A-2:
Please show maximum dimension for the roof overhang. Roof projection shall not project into the 2-ft fire separation distance.
2nd Review Comment: Please revise plan to show 12” maximum roof overhang/projection.
Sheet T1: Title 24 Compliance form – Prescriptive approach
Fenestration: Please revise U-factor to be 0.30 maximum, and SHGC to be 0.23 maximum.
2nd Review Comment: Title 24 calculation was not revised. Please revise Title 24 calculation to show U-factor to be 0.30 maximum, and SHGC to be 0.23 maximum.
Water heater: Plan show tankless water heater – please coordinate and revise accordingly.
2nd Review Comment: Please coordinate and revise Title 24 calculation accordingly.
Sheet S-1:
Section A: Please specify radiant barrier is required underside of roof sheathing, per Energy Requirement.
2nd Review Comment: Please revise plan to specify radiant barrier is required underside of the roof sheathing.
The roof plan did not match with building elevation and the existing roof profile. Please coordinate and revise plan accordingly.
2nd Review Comment: Please provide building elevations.