HomeMy WebLinkAbout271685_2_Corrections.docxRESIDENTIAL PLAN CHECK
COMMENTS
Planning & Building Agency
Building Safety Division
20 Civic Center Plaza
P.O. Box 1988 (M-19)
Santa Ana, CA 92702
(714) 647-5800
www.santa-ana.org
PLAN CHECK NO:
101105687
PROJECT ADDRESS:
2226 S Halladay St
PLAN CHECK ENGINEER:
Ahangian, KathyTEL:714
647-5812
EMAIL:
Kahangian@santa-ana.orgFAX:714
647-5897
TYPE OF CONSTRUCTION:
V B
OCCUPANCY CLASSIFICATION(S):
R-3, U
PLAN CHECK DATES:
REMARKS/RECHECK ITEMS:
APPLICATION
1/20/2021
INITIAL REVIEW
2/23/2021
EXPIRATION
7/19/2021
RECHECKS:
1.
PROJECT APPLICANT CONTACT PERSON:
2.
Lucio Reveles
3.
TEL:
(949)228-1173
FAX:
VALUATION: $10,000.00
EMAIL:
permitsla@freedomforever.com
FLOOD ZONE: X-0602320278J
Note: Numbers in parenthesis (unless otherwise noted) refer to code sections of the 2019 California Residential Code (CRC); 2019 California Building Code (CBC); CMC = 2019 California Mechanical Code; CPC = 2019 California Plumbing Code; CEC = 2019 California Electrical Code; T = Table; ICC = International Code Council.All items noted on this plan check report must be addressed. If you feel that an item is not applicable to your project, note “N/A” and discuss the reason with the plan checker.Please indicate the sheet number and detail to the right of each correction, or note the number on the plans where the correction is made. Resubmit marked original, calculations and this correction sheet. A separate sheet for response may be used.Resubmit 2corrected sets of plans.Meetings between the project applicant/designer and the plan reviewer shall be by appointment only. Please call (714) 647-5812 for an appointment.
Please see corrections on submitted plans. Red marked set must be returned with revised plans. Plans resubmitted without the red markup set may result in delayed review time and additional plancheck fees.
All drawings and supporting documents shall be prepared, stamped, and signed by a California licensed architect or registered professional engineer. (CRC R301.1.3, CBC 107.1 and 107.3.4.1).
Provide complete dimensioned roof framing plan.
Justify existing roof rafters can take load from uplift ( show number of attachments to each rafter and exact location of each attachment on the rafter)
Justify the connection of the roof rafters to the walls can take uplift forces.