Loading...
HomeMy WebLinkAbout282629_2_Corrections.docxRESIDENTIAL PLAN CHECK COMMENTS Planning & Building Agency Building Safety Division 20 Civic Center Plaza P.O. Box 1988 (M-19) Santa Ana, CA 92702 (714) 647-5800 www.santa-ana.org PLAN CHECK NO: 101108976 PROJECT ADDRESS: 1013 1/2 S Cypress Ave PLAN CHECK ENGINEER: Le, TungTEL:714 647-5896 EMAIL: Tle10@santa-ana.orgFAX:714 647-5897 TYPE OF CONSTRUCTION: V B OCCUPANCY CLASSIFICATION(S): R-3, U PLAN CHECK DATES: REMARKS/RECHECK ITEMS: APPLICATION 12/21/2021 INITIAL REVIEW 1/20/2022 EXPIRATION 6/19/2022 RECHECKS: 1.1/31/2022 PROJECT APPLICANT CONTACT PERSON: 2. Cobra Roushanzamir 3. TEL: (714)328-5888 FAX: VALUATION: $85,000.00 EMAIL: wbbak@ca.rr.com FLOOD ZONE: X-0602320276J Note: Numbers in parenthesis (unless otherwise noted) refer to code sections of the 2019 California Residential Code (CRC); 2019 California Building Code (CBC); CMC = 2019 California Mechanical Code; CPC = 2019 California Plumbing Code; CEC = 2019 California Electrical Code; T = Table; ICC = International Code Council.All items noted on this plan check report must be addressed. If you feel that an item is not applicable to your project, note “N/A” and discuss the reason with the plan checker.Please indicate the sheet number and detail to the right of each correction, or note the number on the plans where the correction is made. Resubmit marked original, calculations and this correction sheet. A separate sheet for response may be used.Resubmit 3corrected sets of plans. The applicant shall obtain clearances/approvals for the following, prior to building permit issuance: -Planning Division approval on the corrected/final set of drawings (647-5804). Previously approved plans should be submitted to expedite the process. -Police Department approval on the corrected/final set of drawings (647-5840). -Public Works Agency approval (647-5039). - School District Compliance Certificate; and a copy of the building permit application, signed by the plan check engineer, shall be required by the School District to verify the scope of the work. Sheet 1: Please specify “A minimum 1.0 kWdc photovoltaic system is required to be installed for the proposed ADU. Photovoltaic system may be submitted under a separate permit and shall be installed prior to building frame inspection request.” 2nd Review Comment: No response provided nor plan was revised. Please comply with the comment above. Sheet 3 & 4: Cool roof is required. In addition to the ESR#, a CRRC (Cool Roof Rating Council) number is required to be specified on the plan. 2nd Review Comment: No response provided nor plan was revised. Please comply with the comment above. Sheet 6: On the plan, please show/provide whole-house vent. 2nd Review Comment: No response provided nor plan was revised. Please comply with the comment above. Sheet 7 & 8: Please omit sheet 7 & 8 since structural information are provided on the structural sheets. 2nd Review Comment: No response provided nor plan was revised. Please comply with the comment above. The resubmittal were incomplete. Please provide three complete sets of plans for final review and approval; partial submittal is not acceptable.