HomeMy WebLinkAbout278988_3_Corrections.docx
PLAN CHECK NO:
101107833
PROJECT ADDRESS:
1016 N Flower St
PLAN CHECK ENGINEER:
Lee, WayneTEL:714
647-5848
EMAIL:
wlee@santa-ana.orgFAX:714
647-5897
TYPE OF CONSTRUCTION:
V B
OCCUPANCY CLASSIFICATION(S):
R-3, U
PLAN CHECK DATES:
REMARKS/RECHECK ITEMS:
APPLICATION
8/31/2021
INITIAL REVIEW
9/28/2021
EXPIRATION
2/27/2022
RECHECKS:
1.03/16/2022
PROJECT APPLICANT CONTACT PERSON:
2.
Benito Corona
3.
TEL:
(714)371-7176
FAX:
(914)339-8869
VALUATION: $40,000.00
EMAIL:
bcndesigner@sbcglobal.net
FLOOD ZONE: X-0602320144J
Note: Numbers in parenthesis (unless otherwise noted) refer to code sections of the 2019 California Residential Code (CRC); 2019 California Building Code (CBC); CMC = 2019 California Mechanical Code; CPC = 2019 California Plumbing Code; CEC = 2019 California Electrical Code; T = Table; ICC = International Code Council.
The applicant shall obtain clearances/approvals for the following, prior to building permit issuance:
-Planning Division approval on the corrected/final set of drawings (647-5804). Previously
approved plans should be submitted to expedite the process.
-Public Works Agency approval (647-5039).
PLAN CHECK COMMETNS
Sheet T24-1. Add new 5’x6’8” glazed door into section I fenestration design in energy calculation.
STRUCTURAL
At the exterior wall of the kitchen with enlarged opening for the new glazed door, provide lateral force resisting system design along the exterior wall. Provide structural calculation and lateral shear transfer detail at the top and at the bottom of the shear wall.
END OF COMMENTS