HomeMy WebLinkAbout282653_2_Corrections.docxRESIDENTIAL PLAN CHECK
COMMENTS
Planning & Building Agency
Building Safety Division
20 Civic Center Plaza
P.O. Box 1988 (M-19)
Santa Ana, CA 92702
(714) 647-5800
www.santa-ana.org
PLAN CHECK NO:
101108982
PROJECT ADDRESS:
2001 S Towner St
PLAN CHECK ENGINEER:
Lo, JonathanTEL:714
647-5822
EMAIL:
Jlo@santa-ana.orgFAX:714
647-5897
TYPE OF CONSTRUCTION:
V B
OCCUPANCY CLASSIFICATION(S):
R-3, U
PLAN CHECK DATES:
REMARKS/RECHECK ITEMS:
APPLICATION
12/22/2021
INITIAL REVIEW
2/7/2022
EXPIRATION
6/20/2022
RECHECKS:
1.
PROJECT APPLICANT CONTACT PERSON:
2.
Oscar Vega
3.
TEL:
(747)499-1247
FAX:
VALUATION: $38,700.00
EMAIL:
oscar.vega@vecodesigns.com
FLOOD ZONE: X-0602320257J
Note: Numbers in parenthesis (unless otherwise noted) refer to code sections of the 2019 California Residential Code (CRC); 2019 California Building Code (CBC); CMC = 2019 California Mechanical Code; CPC = 2019 California Plumbing Code; CEC = 2019 California Electrical Code; T = Table; ICC = International Code Council.All items noted on this plan check report must be addressed. If you feel that an item is not applicable to your project, note “N/A” and discuss the reason with the plan checker.Please indicate the sheet number and detail to the right of each correction, or note the number on the plans where the correction is made. Resubmit marked original, calculations and this correction sheet. A separate sheet for response may be used.Resubmit corrected sets of plans.Meetings between the project applicant/designer and the plan reviewer shall be by appointment only. Please call (714) 647-5822 for an appointment.
The applicant shall obtain clearances/approvals for the following, prior to building permit issuance:
Planning Division approval on the corrected/final set of drawings (647-5804). Previously approved plans should be submitted to expedite the process.
Public Works Agency approval (647-5039).
School District Approval; and a copy of the school fee worksheet, completed by the plan check engineer, shall be required by the School District to verify the scope of the work. Comments have been provided on drawing and calculation hard copies in relation to all comments below. These may be picked up at Building and Planning department at applicants’ discretion.DrawingsSheet A-2.2Provide framing for new attic access.Sheet A-4.1Provide ridge beam connection detail at valley.Sheet S-0Final structural plans shall be stamped, signed, and dated by a California licensed architect or civil engineer.Provide wind and seismic project parameters in notes.Sheet S-1Provide North Arrow on plan.Provide detail reference at new ridge framing.Provide detail for rafter connection at valley/ bearing wall.Provide strap between existing and new north wall for shear transfer.Provide header size and new opening in existing Bedroom 3.Provide shear wall length for west shear wall on plan.Provide strap between new 4x12 and existing wall for shear transfer.Provide calculation to justify shallower beam is adequate if 4x12 to be ripped down.Sheet SD-1Detail 1 – Extend shear wall down to mud sill or provide alternate shear transfer all the way to footing.Detail 2 – Provide girder to post cap.Detail 2 – Provide kicker connection to floor joist.Detail 2 – Provide material of support above footing.Detail 2 – Add (2) #4 bars T&B each way in footing.Detail 6 – Use 16d nails at ceiling joist to rafter connections.Detail 6 – Provide shear transfer from vertical 2x blocking to shearwall.Detail 9 – Use (5) – 16d at ceiling joist to rafter connection.Detail 11 – Post is referenced per plan, but no post is provided on plan. Please provide.Detail 13 – Verify the floor joist is flush with girder, detail 2 and 3 show floor joist above girder.Detail 14 - Extend shear wall down to mud sill or provide alternate shear transfer all the way to footing.CalculationsFinal structural calculations shall be stamped, signed, and dated by a California licensed architect or civil engineer.(End of Comment)