HomeMy WebLinkAbout285906_1_Corrections.docxRESIDENTIAL PLAN CHECK
COMMENTS
Planning & Building Agency
Building Safety Division
20 Civic Center Plaza
P.O. Box 1988 (M-19)
Santa Ana, CA 92702
(714) 647-5800
www.santa-ana.org
PLAN CHECK NO:
101109919
PROJECT ADDRESS:
328 E Harwood Pl Unit# 2
PLAN CHECK ENGINEER:
Lo, JonathanTEL:714
647-5822
EMAIL:
Jlo@santa-ana.orgFAX:714
647-5897
TYPE OF CONSTRUCTION:
V B
OCCUPANCY CLASSIFICATION(S):
R-3, U
PLAN CHECK DATES:
REMARKS/RECHECK ITEMS:
APPLICATION
3/28/2022
INITIAL REVIEW
4/8/2022
EXPIRATION
9/24/2022
RECHECKS:
1.
PROJECT APPLICANT CONTACT PERSON:
2.
Erica Perez
3.
TEL:
(818)416-3855
FAX:
VALUATION: $49,000.00
EMAIL:
e.perez@vbsca.com
FLOOD ZONE: X-0602320276J
Note: Numbers in parenthesis (unless otherwise noted) refer to code sections of the 2019 California Residential Code (CRC); 2019 California Building Code (CBC); CMC = 2019 California Mechanical Code; CPC = 2019 California Plumbing Code; CEC = 2019 California Electrical Code; T = Table; ICC = International Code Council.All items noted on this plan check report must be addressed. If you feel that an item is not applicable to your project, note “N/A” and discuss the reason with the plan checker.Please indicate the sheet number and detail to the right of each correction, or note the number on the plans where the correction is made. Resubmit marked original, calculations and this correction sheet. A separate sheet for response may be used.Resubmit corrected sets of plans.Meetings between the project applicant/designer and the plan reviewer shall be by appointment only. Please call (714) 647-5822 for an appointment.
5. The applicant shall obtain clearances/approvals for the following, prior to building permit issuance:
☒Planning Division approval on the corrected/final set of drawings (647-5804). Previously approved plans should be submitted to expedite the process.
☒Public Works Agency approval (647-5039).
☐Fire Department approval on the corrected/final set of drawings (647-5839 or 647-5700).
☒Police Department approval on the corrected/final set of drawings (647-5840).
☒School District Approval; and a copy of the school fee worksheet, completed by the plan check engineer, shall be required by the School District to verify the scope of the work.
☐Proof of Worker's Compensation Insurance shall be required at the time of permit issuance.
☐Grading Permit. Application is made through the Building Safety Division (647-5800) and the plan review is by the Public Works Agency (647-5039).Comments have been provided on drawing and calculation hard copies in relation to all comments below. These may be picked up at Building and Planning department at applicants’ discretion.DrawingsSheet A-0
Provide the following design data on the first sheet (R106.1.1)
☒Occupancy groups (R-3/U)
☒Type of construction (V-B)
☒Automatic Fire Sprinkler (YES or NO)
☐Number of stories.
☒Flood Zone: X
☐Flood Zone: A
☐Floor area per occupancy group, including the existing structure(s)
☒Construction shall comply with the 2019 CRC, CBC, CPC, CMC, CEC, California Green Building Code, and California Energy Efficiency Standards Code editions.Revise Code years to 2019 Codes.Sheet A-2Note on plan: Mechanical, electrical and plumbing are not part of this plan review and approval. MEP are subject to building field inspection.Provide exterior landing dimensions.Provide hood/exhaust over kitchen range (100 CFM min)Sheet A-3Detail 1 – Provide shear transfer through eave connection detail.Verify all detail references to sheet A4, sheet A4 provided is elevation sheet.Provide framing detail for new round opening in ceiling/roof.
Attic access and Ventilations –
☒Show location(s) of 22" x 30" attic access with 30" minimum clear headroom. (R807.1)
☐Show on the plans - attic vent locations, type and size (area = 1/150 of the attic space). Provide an attic cross ventilation summary; on the plans indicate the total area required versus provided. (R806.1)☒For an FAU located in the attic, provide a minimum access of 22 x 30 inches, a 24-inch wide walkway, a 30-inch deep work platform, and electric light outlet adjacent to the furnace and switched by the opening. (CMC 904.11 & 305)No eave projection permitted at wall along property line. (E) projection must be demolished, revise elevations and details accordingly.Provide post installed anchorage at detail 4/A5 callouts over existing foundation.Current lateral system does not meet prescriptive requirements. Maximum distance to nearest shear wall is 8’-0”. Add shear wall (2’-8” min required with holdown) as needed on east side (plan north) or provide calculations for current layout stamped and signed by licensed engineer. Sheet A-5Detail 12 – Provide post installed option information including epoxy type and ICC. (End of Comment)