HomeMy WebLinkAbout286447_1_Corrections.docxRESIDENTIAL PLAN CHECK
COMMENTS
Planning & Building Agency
Building Safety Division
20 Civic Center Plaza
P.O. Box 1988 (M-19)
Santa Ana, CA 92702
(714) 647-5800
www.santa-ana.org
PLAN CHECK NO:
101110096
PROJECT ADDRESS:
2509 S Center St
PLAN CHECK ENGINEER:
Lo, JonathanTEL:714
647-5822
EMAIL:
Jlo@santa-ana.orgFAX:714
647-5897
TYPE OF CONSTRUCTION:
V B
OCCUPANCY CLASSIFICATION(S):
R-3
PLAN CHECK DATES:
REMARKS/RECHECK ITEMS:
APPLICATION
4/13/2022
INITIAL REVIEW
4/24/2022
EXPIRATION
10/10/2022
RECHECKS:
1.
PROJECT APPLICANT CONTACT PERSON:
2.
Ha Nguyen
3.
TEL:
(714)326-3124
FAX:
VALUATION: $80,000.00
EMAIL:
win.nguyen.ent@gmail.com
FLOOD ZONE: X-0602320259J
Note: Numbers in parenthesis (unless otherwise noted) refer to code sections of the 2019 California Residential Code (CRC); 2019 California Building Code (CBC); CMC = 2019 California Mechanical Code; CPC = 2019 California Plumbing Code; CEC = 2019 California Electrical Code; T = Table; ICC = International Code Council.All items noted on this plan check report must be addressed. If you feel that an item is not applicable to your project, note “N/A” and discuss the reason with the plan checker.Please indicate the sheet number and detail to the right of each correction, or note the number on the plans where the correction is made. Resubmit marked original, calculations and this correction sheet. A separate sheet for response may be used.Resubmit corrected sets of plans.Meetings between the project applicant/designer and the plan reviewer shall be by appointment only. Please call (714) 647-5822 for an appointment.
5. The applicant shall obtain clearances/approvals for the following, prior to building permit issuance:
☒Planning Division approval on the corrected/final set of drawings (647-5804). Previously approved plans should be submitted to expedite the process.
☒Public Works Agency approval (647-5039).
☐Fire Department approval on the corrected/final set of drawings (647-5839 or 647-5700).
☐Police Department approval on the corrected/final set of drawings (647-5840).
☒School District Approval; and a copy of the school fee worksheet, completed by the plan check engineer, shall be required by the School District to verify the scope of the work.
☐Proof of Worker's Compensation Insurance shall be required at the time of permit issuance.
☐Grading Permit. Application is made through the Building Safety Division (647-5800) and the plan review is by the Public Works Agency (647-5039).Comments have been provided on drawing and calculation hard copies in relation to all comments below. These may be picked up at Building and Planning department at applicants’ discretion.DrawingsSheet TS
Provide the following design data on the first sheet (R106.1.1)
☐Occupancy groups (R-3/U)
☐Type of construction (V-B)
☒Automatic Fire Sprinkler (YES or NO)
☐Number of stories.
☒Flood Zone: X
☐Flood Zone: A
☐Flood Zone: AE
☐Floor area per occupancy group, including the existing structure(s)
☐Construction shall comply with the 2019 CRC, CBC, CPC, CMC, CEC, California Green Building Code, and California Energy Efficiency Standards Code editions.Sheet A3Note on plan: Mechanical, electrical and plumbing are not part of this plan review and approval. MEP are subject to building field inspection.Show hood/exhaust fan above new kitchen range (100 CFM min).Sheet S1Note #1: Clarify if new slab on grade is atop existing, details show slab on grade underneath 4” new slab. Sheet S2Verify shear transfer and additional information at WSWH 9’-0” high per note in 9/WSWH2Verify shear transfer at drag from roof diaphragm to roof rafter to SW along grid 2.Provide headers at new closet and bathroom openings.Provide detail from ceiling beam to WSWH.Sheet D1Detail 04 – Verify if new slab on grade is atop existing as shown in detail.Detail 04 – (2) #4 bars minimum in new continuous footings.Detail 07, 13, 23 – Coordinate A35 spacing with Shear Wall Schedule. Sheet WSWH2WSWH sheet to be stamped and signed by licensed engineer.Sheet T24Radiant barrier requirement to be stated on plans or elevations.(End of Comment)