HomeMy WebLinkAbout286661_1_Corrections.docxRESIDENTIAL PLAN CHECK
COMMENTS
Planning & Building Agency
Building Safety Division
20 Civic Center Plaza
P.O. Box 1988 (M-19)
Santa Ana, CA 92702
(714) 647-5800
www.santa-ana.org
PLAN CHECK NO:
101110174
PROJECT ADDRESS:
1225 W Myrtle St Unit# 2
PLAN CHECK ENGINEER:
Lo, JonathanTEL:714
647-5822
EMAIL:
Jlo@santa-ana.orgFAX:714
647-5897
TYPE OF CONSTRUCTION:
V B
OCCUPANCY CLASSIFICATION(S):
R-3, U
PLAN CHECK DATES:
REMARKS/RECHECK ITEMS:
APPLICATION
4/20/2022
INITIAL REVIEW
5/10/2022
EXPIRATION
10/17/2022
RECHECKS:
1.
PROJECT APPLICANT CONTACT PERSON:
2.
David Nguyen
3.
TEL:
(510)650-5499
FAX:
VALUATION: $50,000.00
EMAIL:
httr.3g@gmail.com
FLOOD ZONE: X-0602320257J
Note: Numbers in parenthesis (unless otherwise noted) refer to code sections of the 2019 California Residential Code (CRC); 2019 California Building Code (CBC); CMC = 2019 California Mechanical Code; CPC = 2019 California Plumbing Code; CEC = 2019 California Electrical Code; T = Table; ICC = International Code Council.All items noted on this plan check report must be addressed. If you feel that an item is not applicable to your project, note “N/A” and discuss the reason with the plan checker.Please indicate the sheet number and detail to the right of each correction, or note the number on the plans where the correction is made. Resubmit marked original, calculations and this correction sheet. A separate sheet for response may be used.Resubmit corrected sets of plans.Meetings between the project applicant/designer and the plan reviewer shall be by appointment only. Please call (714) 647-5822 for an appointment.
5. The applicant shall obtain clearances/approvals for the following, prior to building permit issuance:
☒Planning Division approval on the corrected/final set of drawings (647-5804). Previously approved plans should be submitted to expedite the process.
☒Public Works Agency approval (647-5039).
☐Fire Department approval on the corrected/final set of drawings (647-5839 or 647-5700).
☒Police Department approval on the corrected/final set of drawings (647-5840).
☒School District Approval; and a copy of the school fee worksheet, completed by the plan check engineer, shall be required by the School District to verify the scope of the work.
☐Proof of Worker's Compensation Insurance shall be required at the time of permit issuance.
☐Grading Permit. Application is made through the Building Safety Division (647-5800) and the plan review is by the Public Works Agency (647-5039).Comments have been provided on drawing and calculation hard copies in relation to all comments below. These may be picked up at Building and Planning department at applicants’ discretion.DrawingsSheet A1.0
Provide the following design data on the first sheet (R106.1.1)
☐Occupancy groups (R-3/U)
☐Type of construction (V-B)
☐Automatic Fire Sprinkler (YES or NO)
☐Number of stories.
☒Flood Zone: X
☐Flood Zone: A
☐Flood Zone: AE
☐Floor area per occupancy group, including the existing structure(s)
☐Construction shall comply with the 2019 CRC, CBC, CPC, CMC, CEC, California Green Building Code, and California Energy Efficiency Standards Code editions.Provide T3 sheet or remove from Sheet Index.Sheet A2.0Provide drainage and flow direction around new patio.Sheet A3.0Provide U-Factor and SHGC in window schedule.Sheet A4.0Provide new roofing type (Class C min), ICC, and CRRC if applicable on elevations or reference where information is located.Sheet S-2Provide patio diaphragm sheathing on plan or reference where information is located.Provide new hip beam sizes on plan.Verify new ridge beam support on end with no KP.Provide shearwall length for middle shearwall along Grid 1. Detail S2 – Provide number of nailing for new ceiling joist.Detail S2 – Specify fire rated dry wall system on interior for 1 hour rated system.
Attic access and Ventilations –
☐Show location(s) of 22" x 30" attic access with 30" minimum clear headroom. (R807.1)
☐Show on the plans - attic vent locations, type and size (area = 1/150 of the attic space). Provide an attic cross ventilation summary; on the plans indicate the total area required versus provided. (R806.1)
☒For an FAU located in the attic, provide a minimum access of 22 x 30 inches, a 24-inch wide walkway, a 30-inch deep work platform, and electric light outlet adjacent to the furnace and switched by the opening. (CMC 904.11 & 305)Sheet SD-1Detail 5 – Verify 4” slab atop existing 4” slab on grade. Coordinate patio foundation shown in detail 09 and 12. (End of Comment)