HomeMy WebLinkAbout283889_2_Corrections.docxRESIDENTIAL PLAN CHECK
COMMENTS
Planning & Building Agency
Building Safety Division
20 Civic Center Plaza
P.O. Box 1988 (M-19)
Santa Ana, CA 92702
(714) 647-5800
www.santa-ana.org
PLAN CHECK NO:
101109347
PROJECT ADDRESS:
802 E Pomona St
PLAN CHECK ENGINEER:
Lo, JonathanTEL:714
647-5822
EMAIL:
Jlo@santa-ana.orgFAX:714
647-5897
TYPE OF CONSTRUCTION:
V B
OCCUPANCY CLASSIFICATION(S):
R-3, U
PLAN CHECK DATES:
REMARKS/RECHECK ITEMS:
APPLICATION
2/7/2022
INITIAL REVIEW
3/14/2022
EXPIRATION
8/6/2022
RECHECKS:
1.
PROJECT APPLICANT CONTACT PERSON:
2.
Ruben Pena
3.
TEL:
(714)552-5731
FAX:
VALUATION: $15,000.00
EMAIL:
ruben@inkminded.com
FLOOD ZONE: X-0602320276J
Note: Numbers in parenthesis (unless otherwise noted) refer to code sections of the 2019 California Residential Code (CRC); 2019 California Building Code (CBC); CMC = 2019 California Mechanical Code; CPC = 2019 California Plumbing Code; CEC = 2019 California Electrical Code; T = Table; ICC = International Code Council.All items noted on this plan check report must be addressed. If you feel that an item is not applicable to your project, note “N/A” and discuss the reason with the plan checker.Please indicate the sheet number and detail to the right of each correction, or note the number on the plans where the correction is made. Resubmit marked original, calculations and this correction sheet. A separate sheet for response may be used.Resubmit corrected sets of plans.Meetings between the project applicant/designer and the plan reviewer shall be by appointment only. Please call (714) 647-5822 for an appointment.
5. The applicant shall obtain clearances/approvals for the following, prior to building permit issuance:
☒Planning Division approval on the corrected/final set of drawings (647-5804). Previously approved plans should be submitted to expedite the process.
☐Public Works Agency approval (647-5039).
☐Fire Department approval on the corrected/final set of drawings (647-5839 or 647-5700).
☐Police Department approval on the corrected/final set of drawings (647-5840).
☒School District Approval; and a copy of the school fee worksheet, completed by the plan check engineer, shall be required by the School District to verify the scope of the work.
☐Proof of Worker's Compensation Insurance shall be required at the time of permit issuance.
☐Grading Permit. Application is made through the Building Safety Division (647-5800) and the plan review is by the Public Works Agency (647-5039).Comments have been provided on drawing and calculation hard copies in relation to all comments below. These may be picked up at Building and Planning department at applicants’ discretion.Documentation
Energy Conservation – Title 24 Energy forms & calculations
1. Provide documentation to demonstrate compliance with the California Energy Code.
2. Climate zone 8 is used.
3. Compliance forms with signatures must be provided on plans.
7. On the plan, please specify U-factor (0.3 min) and SHGC (0.23 min) for building fenestration, per Title 24 calculation. DrawingsSheet 1ATC Hazards, additional information, designer information, and many notes on sheets are illegible, please reprint notes to be more clear.
Provide the following design data on the first sheet (R106.1.1)
☒Accessor’s Parcel Number (APN)
☐Occupancy groups (R-3/U)
☒Type of construction (V-B)
☐Automatic Fire Sprinkler (YES or NO)
☐Number of stories.
☒Flood Zone: X
☐Flood Zone: A
☐Floor area per occupancy group, including the existing structure(s)
☐Construction shall comply with the 2019 CRC, CBC, CPC, CMC, CEC, California Green Building Code, and California Energy Efficiency Standards Code editions.Sheet 9 in sheet index is not provided, please provide.Sheet 2Provide new wall size for typical non-plumbing wall in plan key.Ensure existing kitchen has artificial lighting, provide existing or new lighting type on electrical plan.Sheet 5Note on plan: Mechanical, electrical and plumbing are not part of this plan review and approval. MEP are subject to building field inspection.All code references in notes shall reference latest 2019.Detail 6 - Provide epoxy embed dimension.Calculations call for 18” wide continuous footing, revise drawings to match calcs.Sheet 6Provide shear wall length and schedule showing type and connections on plan sheet.Provide detail for end of ridge beam at existing side. CalculationsFoundation size does not match drawings, please revise drawings to match.(End of Comment)