HomeMy WebLinkAbout287605_1_Corrections.docxRESIDENTIAL PLAN CHECK
COMMENTS
Planning & Building Agency
Building Safety Division
20 Civic Center Plaza
P.O. Box 1988 (M-19)
Santa Ana, CA 92702
(714) 647-5800
www.santa-ana.org
PLAN CHECK NO:
101110446
PROJECT ADDRESS:
2030 S Poplar St
PLAN CHECK ENGINEER:
Lo, JonathanTEL:714
647-5822
EMAIL:
Jlo@santa-ana.orgFAX:714
647-5897
TYPE OF CONSTRUCTION:
V B
OCCUPANCY CLASSIFICATION(S):
R-3, U
PLAN CHECK DATES:
REMARKS/RECHECK ITEMS:
APPLICATION
5/18/2022
INITIAL REVIEW
5/20/2022
EXPIRATION
11/14/2022
RECHECKS:
1.
PROJECT APPLICANT CONTACT PERSON:
2.
Tom Vo
3.
TEL:
(714)299-4770
FAX:
VALUATION: $50,000.00
EMAIL:
adusb9@gmail.com
FLOOD ZONE: X-0602320257J
Note: Numbers in parenthesis (unless otherwise noted) refer to code sections of the 2019 California Residential Code (CRC); 2019 California Building Code (CBC); CMC = 2019 California Mechanical Code; CPC = 2019 California Plumbing Code; CEC = 2019 California Electrical Code; T = Table; ICC = International Code Council.All items noted on this plan check report must be addressed. If you feel that an item is not applicable to your project, note “N/A” and discuss the reason with the plan checker.Please indicate the sheet number and detail to the right of each correction, or note the number on the plans where the correction is made. Resubmit marked original, calculations and this correction sheet. A separate sheet for response may be used.Resubmit corrected sets of plans.Meetings between the project applicant/designer and the plan reviewer shall be by appointment only. Please call (714) 647-5822 for an appointment.The drawings/information submitted for Building Safety Division review is incomplete. The applicant shall, prior to resubmitting, complete all construction documents to show compliance with the 2019 California Building Standards Code with local amendments and to clearly indicate the scope of work under this building permit application. There may be additional requirements when complete construction drawings and supporting data is submitted for Building Safety Division review.
6. The applicant shall obtain clearances/approvals for the following, prior to building permit issuance:
☒Planning Division approval on the corrected/final set of drawings (647-5804). Previously approved plans should be submitted to expedite the process.
☒Public Works Agency approval (647-5039).
☐Fire Department approval on the corrected/final set of drawings (647-5839 or 647-5700).
☒Police Department approval on the corrected/final set of drawings (647-5840).
☐School District Approval; and a copy of the school fee worksheet, completed by the plan check engineer, shall be required by the School District to verify the scope of the work.
☐Proof of Worker's Compensation Insurance shall be required at the time of permit issuance.
☐Grading Permit. Application is made through the Building Safety Division (647-5800) and the plan review is by the Public Works Agency (647-5039).Comments have been provided on drawing and calculation hard copies in relation to all comments below. These may be picked up at Building and Planning department at applicants’ discretion.DocumentationProvide structural drawings and calculations for garage replacement. Final plans and calculations are to be stamped, signed and dated by a California licensed architect or California registered civil engineer.
Provide on the plans, structural material notes (ex. Lumber species & grade, glu-lam beams, concrete (fc’ = ___ psi (min)), steel reinforcement, special inspection requirements, etc.))DrawingsSheet D-01Provide cover sheet with a project description with a complete and detailed scope of work on the cover sheet of the plans.
Provide the following design data on the first sheet (R106.1.1)
☒Occupancy groups (R-3/U)
☒Type of construction (V-B)
☒Automatic Fire Sprinkler (YES or NO)
☒Number of stories.
☒Flood Zone: X
☐Flood Zone: A
☐Flood Zone: AE
☒Floor area per occupancy group, including the existing structure(s)
☒Construction shall comply with the 2019 CRC, CBC, CPC, CMC, CEC, California Green Building Code, and California Energy Efficiency Standards Code editions.
Provide a complete plot plan showing – (R106.2)
☒Location and size of all structures on the lot.
☒Identify all property lines and easements, streets, etc.
☒Show north arrow.
☐Distances between buildings (main house, detached garage, accessory dwelling unit, etc.).
☒Distances (setbacks) between buildings and property lines.
Dwelling/garage separation –
☒Door between garage and residence shall be solid wood doors not less than 1-3/8 inches in thickness; solid or honeycomb core steel doors not less than 1-3/8 inches thick; or 20-minute fire-rated doors. And doors shall be self-closing and self-latching. (R302.5.1)
☒Where automatic residential fire sprinkler systems are provided in residence and the private garage – doors need only be self-closing and self-latching. (R302.5.1 Exc.)
☒Ducts in the garage and ducts penetrating the walls or ceilings separating the dwelling from the garage shall be constructed of minimum No. 26 gage sheet steel, and shall have no openings into the garage. (R302.5.2)
☒Wall between garage/carport and dwelling – Provide minimum 1/2-inch gypsum board on the garage side; extended from foundation to the roof sheathing. (R302.6)
☒Minimum 5/8-inch Type X gypsum board is required at the underside of floor/ceiling where habitable space is above. Structure(s) supporting floor/ceiling assemblies used for separation shall be protected with 1/2-inch gypsum board. (R302.6) (End of Comment)