Loading...
HomeMy WebLinkAbout283246_3_Corrections.docxTENANT IMPROVEMENT PLAN CHECK COMMENTS COMMENTS Planning & Building Agency Building Safety Division 20 Civic Center Plaza P.O. Box 1988 (M-19) Santa Ana, CA 92702 (714) 647-5800 www.santa-ana.org PLAN CHECK NO: 101109147 PROJECT ADDRESS: 3701 W Moore Ave PLAN CHECK ENGINEER: Lee, WayneTEL:714 647-5848 EMAIL: wlee@santa-ana.orgFAX:714 647-5897 TYPE OF CONSTRUCTION: III B, SPK OCCUPANCY CLASSIFICATION(S): B, F-1, S-1 PLAN CHECK DATES: REMARKS/RECHECK ITEMS: APPLICATION 1/18/2022 INITIAL REVIEW 2/10/2022 EXPIRATION 7/17/2022 RECHECKS: 1.04/25/2022 PROJECT APPLICANT CONTACT PERSON: 2.05/24/2022 Paula Harris 3. TEL: (562)216-5244 FAX: VALUATION: $50,000.00 EMAIL: pharris@kkaia.com FLOOD ZONE: X-0602320258J APPLICABLE CODE: 2019 CALIFORNIA BUILDING CODE (CBC) WITH CITY OF SANTA ANA AMENDMENTSThe applicant shall obtain clearances/approvals for the following prior to building permit issuance: - Planning Division approval on the corrected/final set of drawings (647-5804.) Previously approved plans should be submitted to expedite the process. - Fire Department approval on the corrected/final sets of drawings ((714)573-6100) - Police Department approval on the corrected/final set of drawings (647-5840) - Public Works Agency approval (647-5039)Plan check comments:Comparing with previous package, a number of drawings and structural calculation are not included at this submittal. City will not slip sheets for the applicant or assume any of the previous submittal as part of the approval plans. Please provide complete submittal package at submission for review. Incomplete submittal may cause review delay and rejection.Do not use drop cart for next submittal. Contact permit staff to make an appointment to update the scope of work prior to plan review. See item #1.Sheet C.S. The revision from delta 5 through delta 7 are not part of the original permit (#101108084). Please revise the scope of work to provide full description of the scope after delta 4 revision. The scope of this permit (#101109147) has been modified multiple times by the applicant after first submittal. The scope in city record may no longer match the drawing. At the next submittal, please make an appointment with permit staff to update the scope of work prior to plan check.For your reference, the image below is the scope in our record as your original proposal under this permit. It needs to be updated at the time of next submission.Cloud and delta throughout the drawings to identify the location of the revision.Clearly identify on each sheet.Submit complete (2) sets of plans and (2) sets of structural calculations for review and/or approval.Identify what is the revision on sheet D-1.1.2 same as all other sheets.NEW CORRECTION-Based on revised plan, fertigation room (C119) is changed for last submittal:Refer to door #C119 on sheet A-2.1. Doors in any position shall not reduce the required width by more than one-half. This 4-foot wide door swings into the required exterior exit door landing does not comply.Refer to door #C119 on sheet A-2.1:Provideclear space of 18”of the latch side at an interior doorwayfor forward approach on the door pull isde. (CBC 11B-404.2.4.3 & Figure 11B-404.2.4.3 (a))Provide clear space of12” past strike edge of the door on the opposite side to which the door swings if the door is equipped with both a latch and a closer. (CBC Figure 11B-404.2.4.1(c))Show required level clearance on both sides of the door. The front approach level area shall have a length in the direction of door swing of at least 60” and the length opposite the direction of door swing of 48” as measured at right angles to the plane of the door in the closed position. (CBC 11B-404.2.4.1 & Table 11B-404.2.4.1)Show turning space of 60” min shall be provided within the room C119 (CBC 11B-603.2.1).R-Cold freezer panels: STRUCTURAL- Only IP-2 and IP-3 sheets are submittedSubmit complete (2) sets of structural plans and (2) sets of structural calculations.According to IP sheets, there are delta 1 through delta 3 added to this revision. Cloud and delta throughout the drawings to identify the location of the revision. Clearly identify on each sheet.Structural sheet S1.0 through S3.0 are not submitted. If those sheets are part of the scope of this revision package, cloud and delta throughout the drawings to identify the location of the revision. Clearly identify on each sheet.END OF COMMENTS