HomeMy WebLinkAbout286586_2_Corrections.docxRESIDENTIAL PLAN CHECK
COMMENTS
Planning & Building Agency
Building Safety Division
20 Civic Center Plaza
P.O. Box 1988 (M-19)
Santa Ana, CA 92702
(714) 647-5800
www.santa-ana.org
PLAN CHECK NO:
101110143
PROJECT ADDRESS:
810 N Sherry Ln
PLAN CHECK ENGINEER:
Lo, JonathanTEL:714
647-5822
EMAIL:
Jlo@santa-ana.orgFAX:714
647-5897
TYPE OF CONSTRUCTION:
V B
OCCUPANCY CLASSIFICATION(S):
R-3, U
PLAN CHECK DATES:
REMARKS/RECHECK ITEMS:
APPLICATION
4/21/2022
INITIAL REVIEW
5/10/2022
EXPIRATION
10/18/2022
RECHECKS:
1.6/27/2022
PROJECT APPLICANT CONTACT PERSON:
2.
Emmanuel De La Cruz
3.
TEL:
(323)603-1741
FAX:
VALUATION: $13,000.00
EMAIL:
emdelacruz99@gmail.com
FLOOD ZONE: X-0602320164J
Note: Numbers in parenthesis (unless otherwise noted) refer to code sections of the 2019 California Residential Code (CRC); 2019 California Building Code (CBC); CMC = 2019 California Mechanical Code; CPC = 2019 California Plumbing Code; CEC = 2019 California Electrical Code; T = Table; ICC = International Code Council.All items noted on this plan check report must be addressed. If you feel that an item is not applicable to your project, note “N/A” and discuss the reason with the plan checker.Please indicate the sheet number and detail to the right of each correction, or note the number on the plans where the correction is made. Resubmit marked original, calculations and this correction sheet. A separate sheet for response may be used.Resubmit corrected sets of plans.Meetings between the project applicant/designer and the plan reviewer shall be by appointment only. Please call (714) 647-5822 for an appointment.
5. The applicant shall obtain clearances/approvals for the following, prior to building permit issuance:
☒Planning Division approval on the corrected/final set of drawings (647-5804). Previously approved plans should be submitted to expedite the process.
☒Public Works Agency approval (647-5039).
☐Fire Department approval on the corrected/final set of drawings (647-5839 or 647-5700).
☐Police Department approval on the corrected/final set of drawings (647-5840).
☒School District Approval; and a copy of the school fee worksheet, completed by the plan check engineer, shall be required by the School District to verify the scope of the work.
☐Proof of Worker's Compensation Insurance shall be required at the time of permit issuance.
☐Grading Permit. Application is made through the Building Safety Division (647-5800) and the plan review is by the Public Works Agency (647-5039).Comments have been provided on drawing and calculation hard copies in relation to all comments below. These may be picked up at Building and Planning department at applicants’ discretion.DrawingsSheet A-1.0
Provide the following design data on the first sheet (R106.1.1)
☐Occupancy groups (R-3/U)
☐Type of construction (V-B)
☐Automatic Fire Sprinkler (YES or NO)
☐Number of stories.
☒Flood Zone: X
☐Flood Zone: A
☐Flood Zone: AE
☐Floor area per occupancy group, including the existing structure(s)
☒Construction shall comply with the 2019 CRC, CBC, CPC, CMC, CEC, California Green Building Code, and California Energy Efficiency Standards Code editions.2019 codes to be referenced, 2020 codes do not exist. Remove any reference to LA county amendments. Sheet A-2.1Note on plan: Mechanical, electrical and plumbing are not part of this plan review and approval. MEP are subject to building field inspection.Provide smoke detector & carbon monoxide detector outside vicinity of (E) bedroom and (N) bedroom in hallway.Sheet S-SN1Update all code references to current code.Sheet S-S1Identify all detail references as existing unless intended work to be done where detail is called out. Verify/provide new CJ on plans at porch where occurs.Provide detail references around new roof over porch sides including RR and CJ connections, gable ends, and interaction at shown gap between porch and existing roof on north side of porch.Recheck #1: Comment not addressed. Please provide detailing for new framing at porch entry roof including gable ends, and interaction between existing and new at each side of porch. Sheet S-S2, S-S4Detail 2/S-S2 – Verify # or spacing of foundation rebar (2 min ea way)For all detail sheets, clearly identify existing details or details intended to be used for new scope of work. Omit details not used for new work, or specify as existing as needed for clarity.(End of Comment)