HomeMy WebLinkAbout286353_3_Corrections.docxPLAN CHECK COMMENTS
COMMENTS
Planning & Building Agency
Building Safety Division
20 Civic Center Plaza
P.O. Box 1988 (M-19)
Santa Ana, CA 92702
(714) 647-5800
www.santa-ana.org
PLAN CHECK NO:
101110073-77
PROJECT ADDRESS:
2320 S Bristol St
PLAN CHECK ENGINEER:
Le, TungTEL:714
647-5896
EMAIL:
Tle10@santa-ana.orgFAX:714
647-5897
TYPE OF CONSTRUCTION:
V B
OCCUPANCY CLASSIFICATION(S):
A-2
PLAN CHECK DATES:
REMARKS/RECHECK ITEMS:
APPLICATION
4/14/2022
INITIAL REVIEW
4/27/2022
EXPIRATION
10/11/2022
RECHECKS:
1.6/27/22
PROJECT APPLICANT CONTACT PERSON:
2.
Vandana Kelkar
3.
TEL:
(949)554-7051
FAX:
VALUATION: $1,000,000.00
EMAIL:
vkelkar@pmdginc.com
FLOOD ZONE: X-0602320259J
APPLICABLE CODE: 2019 CALIFORNIA BUILDING CODE (CBC) WITH
CITY OF SANTA ANA AMENDMENTS
All items noted on this plan check report must be addressed. If you feel that an item is not applicable to your project, note “N/A” and discuss the reason with the plan checker.Please indicate the sheet number and detail to the right of each correction, or note the number on the plans where the correction is made. Resubmit marked original, calculations and this correction sheet. A separate sheet for response may be used.Resubmit 3corrected sets of plans.The applicant shall obtain clearances/approvals for the following prior to building permit issuance:
- Planning Division approval on the corrected/final set of drawings (647-5804.) Previously approved plans
should be submitted to expedite the process.
- Fire Department approval on the corrected/final sets of drawings ((714)573-6100)
- Police Department approval on the corrected/final set of drawings (647-5840)
- Public Works Agency approval (647-5039)
- Grading Permit. Application is made through the Building Safety Division (647-5800) and the plan review is by
the Public Works Agency (647-5039)
- County of Orange Health Department approval on the corrected/final set of drawings ((714)433-6000)
- School District Compliance Certificate; a copy of the building permit application, signed by the plan check
engineer, shall be required by the School District to verify the scope of work. Refer to the attached handout.Sheet A1.0: Wall type 1C with note 18: Wall type 1C is a metal stud wall per note #18 – Referenced detail 1/A5.0 was not applicable for metal stud wall. Please coordinate and revise detail accordingly. 2nd Review Comment: Response was incomplete. Please provide construction detail of noncombustible wall adjacent to the cooking appliances and hood as required by California Mechanical Code. Clearly cross-reference detail onto the plan. 2nd Review Comment: Exit door 2 at the dining area – Please provide/relocate exit tactile sign to the latch side of the door. Title 24 Energy Compliance forms Please include the Title 24 calculation on the plan for the building envelope. Lighting measures and mechanical compliance forms are reviewed under separate review. 2nd Review Comment: Response was incomplete. Please provide Certificate of Compliance forms for building envelope (form NRCC-ENV-). (End of Comment)