HomeMy WebLinkAbout282141_2_Corrections.docxTENANT IMPROVEMENT
PLAN CHECK COMMENTS
COMMENTS
Planning & Building Agency
Building Safety Division
20 Civic Center Plaza
P.O. Box 1988 (M-19)
Santa Ana, CA 92702
(714) 647-5800
www.santa-ana.org
PLAN CHECK NO:
104108819
PROJECT ADDRESS:
1228 E Pomona St
PLAN CHECK ENGINEER:
So, AnsonTEL:714
647-5830
EMAIL:
aso@santa-ana.orgFAX:714
647-5897
TYPE OF CONSTRUCTION:
V B
OCCUPANCY CLASSIFICATION(S):
B, S-1
PLAN CHECK DATES:
REMARKS/RECHECK ITEMS:
APPLICATION
3/16/2022
INITIAL REVIEW
5/26/2022
EXPIRATION
9/12/2022
RECHECKS:
1.
PROJECT APPLICANT CONTACT PERSON:
2.
Ed Cruz
3.
TEL:
(714)717-2347
FAX:
VALUATION: $1,000.00
EMAIL:
ed@ecprecisdesigns.com
FLOOD ZONE: X-0602320276J
APPLICABLE CODE: 2019 CALIFORNIA BUILDING CODE (CBC) WITH
CITY OF SANTA ANA AMENDMENTS
All items noted on this plan check report must be addressed. If you feel that an item is not applicable to your project, note “N/A” and discuss the reason with the plan checker.Please indicate the sheet number and detail to the right of each correction, or note the number on the plans where the correction is made. Resubmit marked original, calculations and this correction sheet. A separate sheet for response may be used.Resubmit 2corrected sets of plans.Meetings between the project applicant/designer and the plan reviewer shall be by appointment only. Please call (714) 647-5830 for an appointment.Sheet TS1Include the infill of the wall opening under Scope of Work.Sheet A2Show the location of existing opening and cross-reference the infill detail.Provide an infill detail with the following information: size of opening, infill material, rebar size and embedment length, the total number of rebars, and the type of epoxy at the connection between the existing wall and the infilled wall.[END]