PLAN CHECK NO:
101109084
PROJECT ADDRESS:
401 N Garfield St
PLAN CHECK ENGINEER:
So, AnsonTEL:714
647-5830
EMAIL:
aso@santa-ana.orgFAX:714
647-5897
TYPE OF CONSTRUCTION:
V B
OCCUPANCY CLASSIFICATION(S):
R-2
PLAN CHECK DATES:
REMARKS/RECHECK ITEMS:
APPLICATION
2/25/2022
INITIAL REVIEW
3/25/2022
EXPIRATION
8/24/2022
RECHECKS:
1.8/22/2022
PROJECT APPLICANT CONTACT PERSON:
2.
Luis Soto
3.
TEL:
(858)437-4247
FAX:
VALUATION:
EMAIL:
luis@lsrbuilders.com
FLOOD ZONE: X-0602320276J
Note: Numbers in parenthesis (unless otherwise noted) refer to code sections of the 2019 California Residential Code (CRC); 2019 California Building Code (CBC); CMC = 2019 California Mechanical Code; CPC = 2019 California Plumbing Code; CEC = 2019 California Electrical Code; T = Table; ICC = International Code Council.All items noted on this plan check report must be addressed. If you feel that an item is not applicable to your project, note “N/A” and discuss the reason with the plan checker.Please indicate the sheet number and detail to the right of each correction, or note the number on the plans where the correction is made. Resubmit marked original, calculations and this correction sheet. A separate sheet for response may be used.Resubmit 2corrected sets of plans.Meetings between the project applicant/designer and the plan reviewer shall be by appointment only. Please call (714) 647-5830 for an appointment.Sheet T1.0Please cloud all changes with the latest delta-6 revision mark. It appears there are no changes on the title sheet. If there are no changes from the approved plan, exclude the sheet from the revision package.Sheet SP-1.0Planning staff, Pedro Gomez, indicates there are changes to the site plan. However, there are no clouds with the delta-6 revision mark on the site plan. The site plan was compared with the approved site plan, and there are no differences to be found.Sheet SP-2.0Please cloud all changes with the latest delta-6 revision mark. It appears there are no changes on sheet SP-2.0.Sheet D-1.0Please cloud all changes with the latest delta-6 revision mark. It appears there are no changes on sheet D-1.0.Sheet A1.0On the first floor plan, relocate keynote #2 to the doorway.On the second floor plan, the entire second floor has a different design than the approved plan. The wall layouts have changed, but there are no structural revisions. Provide structural revisions for review.The storage room is converted to an “office” room. This room has a bathroom and a closet. To label this room as an office room is not acceptable as an occupant can use this room as a bedroom. A bedroom requires an emergence escape window, which this room does not have.Keynote 17 should be labeled as delta-6, not delta 4.Sheet A-1.1Cloud the entire second floor plan as the design has changed.Sheet A1.4Provide detail of the new 30” roof overhang.Provide fall-protection near the roof access location.Sheet A2.0, A2.1, A2.2It appears there are no changes on sheet A2.0, A2.1, and A2.2. Remove these sheets from the revisions.Additional Comments:Revised structural sheets shall have all proposed revised items clouded and delta’ed appropriately. Provide calculations for any revised gravity elements as well as revised shearwall layout, lengths, types, etc...There are a vast amount of lateral system revisions.Verify new enlarged storage in architectural drawings are accounted for in design with required storage live loads.