PLAN CHECK NO:
101112079
PROJECT ADDRESS:
2514 N Alona St
PLAN CHECK ENGINEER:
Huang, GaryTEL:714
647-5862
EMAIL:
Ghuang@santa-ana.orgFAX:714
647-5897
TYPE OF CONSTRUCTION:
V B
OCCUPANCY CLASSIFICATION(S):
R-3, U
PLAN CHECK DATES:
REMARKS/RECHECK ITEMS:
APPLICATION
9/21/2022
INITIAL REVIEW
11/3/2022
EXPIRATION
3/20/2023
RECHECKS:
1.
PROJECT APPLICANT CONTACT PERSON:
2.
Ben Stanphill
3.
TEL:
(714)356-5206
FAX:
VALUATION:
EMAIL:
ben.stanphill@gmail.com
FLOOD ZONE: X-0602320144J
GUIDELINES:
Comments contained within this report reflect only those of the Building and Safety Division. Additional comments or corrective action may be required by other Departments and/or outside Agencies
This Plan Review Report and all subsequent code references are based upon the most recent version(s) of the 2019 California Building Codes (CBC, CRC, CFC, CEC, CPC, CMC, CGBSC, and CEES)
The approval of plans and any supporting documents does not permit the violation of any section of the adopted building codes or other pertinent local ordinances, or state and federal laws
All listed plan review comments must be adequately addressed before a building permit can be issued
Please indicate the sheet number and detail to the right of each correction, or note the number on the plans where the correction is made. Resubmit marked original, calculations and this correction sheet. A separate sheet for response may be used.
Please see correction on submitted plans. Red marked set must be returned with revised plans. Plans resubmitted without the red markup set may result in delayed review time and additional plan check fees.
PLAN REVIEW COMMENTS:
Applicant shall address all the checked‘☒’ correction comments below before resubmitting plans to Building Safety for recheck.
Sheet 1.1
This background does not match architectural background on Sheet A-1.2 at grid line A. There are no room to place (N) shear wall per Sheet A-1.2
At grid line A’, arch’l shown (N) wall is 20’ away from grind line A. Please verify and revise location. EOR to verify if (E)FJ is adequate
Red marked comment set is available to pick-up at the City Hall. (End of Comment)