PLAN CHECK NO:
101111738
PROJECT ADDRESS:
1926 S Hickory St Unit# 3
PLAN CHECK ENGINEER:
Lo, JonathanTEL:714
647-5822
EMAIL:
Jlo@santa-ana.orgFAX:714
647-5897
TYPE OF CONSTRUCTION:
V B
OCCUPANCY CLASSIFICATION(S):
R-3
PLAN CHECK DATES:
REMARKS/RECHECK ITEMS:
APPLICATION
8/23/2022
INITIAL REVIEW
8/26/2022
EXPIRATION
2/19/2023
RECHECKS:
1.9/29/2022
PROJECT APPLICANT CONTACT PERSON:
2.
Dean Haney
3.
TEL:
(614)886-3770
FAX:
VALUATION:
EMAIL:
Haney.Dean@gmail.com
FLOOD ZONE: X-0602320276J
Note: Numbers in parenthesis (unless otherwise noted) refer to code sections of the 2019 California Residential Code (CRC); 2019 California Building Code (CBC); CMC = 2019 California Mechanical Code; CPC = 2019 California Plumbing Code; CEC = 2019 California Electrical Code; T = Table; ICC = International Code Council.All items noted on this plan check report must be addressed. If you feel that an item is not applicable to your project, note “N/A” and discuss the reason with the plan checker.Please indicate the sheet number and detail to the right of each correction, or note the number on the plans where the correction is made. Resubmit marked original, calculations and this correction sheet. A separate sheet for response may be used.Resubmit corrected sets of plans.Meetings between the project applicant/designer and the plan reviewer shall be by appointment only. Please call (714) 647-5822 for an appointment.
5. The applicant shall obtain clearances/approvals for the following, prior to building permit issuance:
☒Planning Division approval on the corrected/final set of drawings (647-5804). Previously approved plans should be submitted to expedite the process.
☐Public Works Agency approval (647-5039).
☐Fire Department approval on the corrected/final set of drawings (647-5839 or 647-5700).
☐Police Department approval on the corrected/final set of drawings (647-5840).
☐School District Approval; and a copy of the school fee worksheet, completed by the plan check engineer, shall be required by the School District to verify the scope of the work.
☐Proof of Worker's Compensation Insurance shall be required at the time of permit issuance.
☐Grading Permit. Application is made through the Building Safety Division (647-5800) and the plan review is by the Public Works Agency (647-5039).Comments have been provided on drawing and calculation hard copies in relation to all comments below. These may be picked up at Building and Planning department at applicants’ discretion.DocumentationSections for revised garage conversion are not provided. All sheets affected by revision must be revised accordingly and submitted for revision. This includes plans, elevations, sections, details, etc.PC #2: Comment not addressed, all sheets in the originally approved set that is affected by revisions MUST be changed and submitted in revision submittal. This includes building sections for garage to ADU conversion and whether there is new ceiling under roof rafters or exposed. There cannot be any contradicting information on originally approved set and new revision set.The open space area and insulation is revised with proposed revision. A revised Title 24 shall be provided for revision. Please ensure Title 24 for both ADU and JADU are included.PC #2: Comment has not been addressed, revised Title 24 for ADU revision must be completed. Also, T24 must be provided for JADU and ADU separately. Rafter Tie design cannot be more than 1/3 the height from top plate to ridge, else a ridge beam is to be designed with support down to foundation. Rafter tie at height designed cannot act as connection for top of roof rafters. Otherwise justify load path in designed members including lateral design.PC #2: Provide design for new ridge beam, posts, and existing foundation. There is no ridge beam sized on sheet S2. Provide new roof material, class, ICC #, CRRC #, and ensure this new roof is applied in new Title 24 for ADU.(End of Comment)