HomeMy WebLinkAbout294873_1_Corrections.docxTENANT IMPROVEMENT
PLAN CHECK COMMENTS
COMMENTS
Planning & Building Agency
Building Safety Division
20 Civic Center Plaza
P.O. Box 1988 (M-19)
Santa Ana, CA 92702
(714) 647-5800
www.santa-ana.org
PLAN CHECK NO:
101112690
PROJECT ADDRESS:
500 W Santa Ana Blvd
PLAN CHECK ENGINEER:
Lee, WayneTEL:714
647-5848
EMAIL:
wlee@santa-ana.orgFAX:714
647-5897
TYPE OF CONSTRUCTION:
II A, SPK
OCCUPANCY CLASSIFICATION(S):
A-3, B, E, U
PLAN CHECK DATES:
REMARKS/RECHECK ITEMS:
APPLICATION
11/9/2022
INITIAL REVIEW
11/23/2022
EXPIRATION
5/8/2023
RECHECKS:
1.
PROJECT APPLICANT CONTACT PERSON:
2.
Gabriela Aleman
3.
TEL:
(714)625-8325
FAX:
VALUATION: $25,000.00
EMAIL:
GALEMAN@AES-CONSULTANTS.COM
FLOOD ZONE:
APPLICABLE CODE: 2019 CALIFORNIA BUILDING CODE (CBC) WITH
CITY OF SANTA ANA AMENDMENTSPlease indicate the sheet number and detail to the right of each correction, or note the number on the plans where the correction is made.This review does not include mechanical, plumbing, fire sprinkler system, or electrical work. Separate plans, applications, fees, plan checks, and permits are required for mechanical, plumbing, fire sprinkler systems, and electrical work. Call 647-5800 for information.The applicant shall obtain clearances/approvals for the following prior to building permit issuance:
- Planning Division approval on the corrected/final set of drawings (647-5804.) Previously approved plans
should be submitted to expedite the process.
- Fire Department approval on the corrected/final sets of drawings ((714)573-6100)
- Police Department approval on the corrected/final set of drawings (647-5840)Please indicate type of construction and occupancy group on the cover sheet, S0.0. The information can be found on the first page of this comment per City’s record.Please provide a simple site plan showing the location of the property and location of the scope.Please provide an existing floor plan and a proposed floor plan at the penthouse level, showing the existing, new and removed non-structural partitions with different legend. On the floor plan layout, provide dimensions to locate the new stud walls. Label all the use of each space/room.Please add a note to clarify that whether the existing penthouse where the new equipment located is for machinery room only.Sheet S2.2. Top of the penthouse. Please clarify the new equipment location with dimensions. If guards are needed, provide design, elevation and structural connection detail on plan. (CBC 1015.6)Minimum 42” high Guards shall be provided where various components that require service are located within 10 feet of a roof edge or open side of a walking surface and such edge or open side is located more than 30 inches above the floor, roof or grade below. The guard shall extend not less than 30 inches beyond each end of such components. The guard shall be constructed so as to prevent the passage of a sphere 21 inches in diameter.Detail 12/S3.0. Please clarify the dimensions of the spacing distance “D” in the detail.END OF COMMENTS