HomeMy WebLinkAbout295925_1_Corrections.docxRESIDENTIAL PLAN CHECK COMMENTS Planning & Building Agency Building Safety Division 20 Civic Center Plaza P.O. Box 1988 (M-19) Santa Ana, CA 92702 (714) 647-5800 www.santa-ana.org PLAN CHECK NO: 102113038 PROJECT ADDRESS: 1050 W Chestnut Ave PLAN CHECK ENGINEER: Huang, GaryTEL:714 647-5862 EMAIL: Ghuang@santa-ana.orgFAX:714 647-5897 TYPE OF CONSTRUCTION: V B OCCUPANCY CLASSIFICATION(S): R-3 PLAN CHECK DATES: REMARKS/RECHECK ITEMS: APPLICATION 12/7/2022 INITIAL REVIEW 12/9/2022 EXPIRATION 6/5/2023 RECHECKS: 1. PROJECT APPLICANT CONTACT PERSON: 2. Elizabeth Banales 3. TEL: (323)875-8888 FAX: VALUATION: $100,000.00 EMAIL: lizbanalesrealtor@gmail.com FLOOD ZONE: X-0602320257J GUIDELINES: Comments contained within this report reflect only those of the Building and Safety Division. Additional comments or corrective action may be required by other Departments and/or outside Agencies This Plan Review Report and all subsequent code references are based upon the most recent version(s) of the 2019 California Building Codes (CBC, CRC, CFC, CEC, CPC, CMC, CGBSC, and CEES) The approval of plans and any supporting documents does not permit the violation of any section of the adopted building codes or other pertinent local ordinances, or state and federal laws All listed plan review comments must be adequately addressed before a building permit can be issued Please indicate the sheet number and detail to the right of each correction, or note the number on the plans where the correction is made. Resubmit marked original, calculations and this correction sheet. A separate sheet for response may be used. Please see correction on submitted plans. Red marked set must be returned with revised plans. Plans resubmitted without the red markup set may result in delayed review time and additional plan check fees. PLAN REVIEW COMMENTS: Applicant shall address all the checked‘☒’ correction comments below before resubmitting plans to Building Safety for recheck. ☒1. The applicant shall obtain clearances/approvals for the following, prior to building permit issuance: ☒Planning Division approval on the corrected/final set of drawings (647-5804). Previously approved plans should be submitted to expedite the process. ☐Fire Department approval on the corrected/final set of drawings (647-5839 or 647-5700). ☐Police Department approval on the corrected/final set of drawings (647-5840). ☒Public Works Agency approval (647-5039). ☐Proof of Worker's Compensation Insurance shall be required at the time of permit issuance. ☐School District Approval; and a copy of the school fee worksheet, completed by the plan check engineer, shall be required by the School District to verify the scope of the work. ☐Grading Permit. Application is made through the Building Safety Division (647-5800) and the plan review is by the Public Works Agency (647-5039). ☐2. This project is in a special flood hazard area designated on the flood insurance rate map (FIRM) as zone A or AE. This zone requires that the lowest finish floor elevation (including basement) of the structure shall be at (or above) base flood elevation determined by a hydrology study for the A zone, or at (or above) the base flood elevation specified for the AE zone, on the flood insurance rate map. All elevations must be referenced to the National Geodetic Vertical Datum. Reference should be made to the Flood Plain Management Ordinance, Santa Ana Municipal Code, Chapter 7, for complete requirements. Drawings shall show compliance with said ordinance including noting flood zone and finish floor elevation." ☐3. Note on plans: "A Federal Emergency Management Agency National Flood Insurance Program ELEVATION CERTIFICATE shall be completed by a California Licensed Land Surveyor or California Registered Civil Engineer who is authorized to practice land surveying. The completed ELEVATION CERTIFICATE must be submitted to the Building Inspector at the time of foundation inspection, and a FINAL CERTIFICATE must be submitted at the time of final inspection." ☒4. Provide a project description with a complete and detailed scope of work on the cover sheet of the plans. ☒5. Note on plan: All concealed work installed without permits must be exposed for inspection to the satisfaction of the Building Inspector. This includes methods of attachment and all footings, structural members, mechanical, electrical, plumbing and insulation. ☐6. Provide the following design data on the first sheet (R106.1.1) ☐Occupancy groups (R-3/U) ☐Type of construction (V-B) ☐Automatic Fire Sprinkler (YES or NO) ☐Number of stories. ☐Floor area per occupancy group, including the existing structure(s) ☐Construction shall comply with the 2019 CRC, CBC, CPC, CMC, CEC, California Green Building Code, and California Energy Efficiency Standards Code editions. ☒7. Note on plan: Mechanical, electrical and plumbing are not part of this plan review and approval. MEP are subject to building field inspection. ☒8. Carbon Monoxide Alarms – Provide carbon monoxide alarms at outside of each sleeping area, in the immediate vicinity of the bedroom(s); on every level of a dwelling unit including basements. (R315) Energy Conservation – Title 24 Energy forms & calculations ☒1. Provide documentation to demonstrate compliance with the California Energy Code. ☒2. Climate zone 8 is used. ☒3. Compliance forms with signatures must be provided on plans. ☐4. Kitchen shall be vented to the outside. On the plan, please show exhaust fan(s) in kitchen (100 cfm minimum). ☐5. New building, or addition more than 1000 sq.ft. – Provide Whole house ventilation. On the plan, please provide/show method of whole house ventilation in compliance with ASHRAE Standard 62.2. – provide complete notes, details and calculations. (150.0(o)) ☐6. Provide building sections to show building envelope, including wall, floor, and roof/ceiling insulation, per Title 24 calculation. ☒7. On the plan, please specify U-factor (not higher than 0.3) and SHGC (not higher than 0.23 min) for building fenestration, per Title 24 calculation. ☐8. Photovoltaic system is required for all newly constructed low-rise SFD including detached ADU, and Multifamily buildings. On the plan, please specify minimum system size (in KW) in accordance with the Title 24 calculation. (Section 150.1(c)14; 150.1(b)(1))☒Additional Review Comment: Sheet A-3.0 Detail 1 Provide complete construction detail of water-heater enclosure including framing size, framing spacing, roofing material, roof slope, and connection to (E) building for further review Provide water heater enclosure dimension Red marked comment set is available to pick-up at the City Hall. (End of Comment)