HomeMy WebLinkAbout292020_3_Corrections.docxPLAN CHECK COMMENTS
COMMENTS
Planning & Building Agency
Building Safety Division
20 Civic Center Plaza
P.O. Box 1988 (M-19)
Santa Ana, CA 92702
(714) 647-5800
www.santa-ana.org
PLAN CHECK NO:
101111780
PROJECT ADDRESS:
3001 S Susan St
PLAN CHECK ENGINEER:
Le, TungTEL:714
647-5896
EMAIL:
Tle10@santa-ana.orgFAX:714
647-5897
TYPE OF CONSTRUCTION:
III B, SPK
OCCUPANCY CLASSIFICATION(S):
B, F-1
PLAN CHECK DATES:
REMARKS/RECHECK ITEMS:
APPLICATION
9/8/2022
INITIAL REVIEW
10/11/2022
EXPIRATION
3/7/2023
RECHECKS:
1.11/23/2022
PROJECT APPLICANT CONTACT PERSON:
2.2/28/23
Michael Bates
3.
TEL:
(562)426-3453
FAX:
VALUATION: $14,000.00
EMAIL:
mb@mbtechnicalservices.com
FLOOD ZONE: X-0602320258J
APPLICABLE CODE: 2019 CALIFORNIA BUILDING CODE (CBC) WITH
CITY OF SANTA ANA AMENDMENTS
All items noted on this plan check report must be addressed. If you feel that an item is not applicable to your project, note “N/A” and discuss the reason with the plan checker.Please indicate the sheet number and detail to the right of each correction, or note the number on the plans where the correction is made. Resubmit marked original, calculations and this correction sheet. A separate sheet for response may be used.Resubmit 2corrected sets of plans.The applicant shall obtain clearances/approvals for the following prior to building permit issuance:
- Planning Division approval on the corrected/final set of drawings (647-5804.) Previously approved plans
should be submitted to expedite the process.
- Fire Department approval on the corrected/final sets of drawings ((714)573-6100)
- Police Department approval on the corrected/final set of drawings (647-5840)
- Public Works Agency approval (647-5039)Sheet 3: Floor PlanThe location of the proposed spray booth is close to the existing exit doorway – Please show / provide additional exit sign so that it would not be blocked by the proposed spray booth. Sheet 4 & 5: The prefabricated spray booth must be tested and listed by a nationally recognized laboratory (commonly use are UL, ICC, ETL). On the plan, please specify the listing agency and listing number for the prefabricated spray booth. 2nd3rdReview Comment: All prefabricated spray booths must be tested and listed by a nationally recognized laboratory. Structural calculation provided only for equipment anchorage. Please comply with the original comment above. Reminder: All plans shall be stamped, signed and dated by the engineer of record, and plans must be legible. **ADDITIONAL PLAN CHECK FEE WILL BE REQUIRED IF PLAN CHECK COMMENTS ABOVE ARE NOT RESOLVED.
(End of Comment)