HomeMy WebLinkAbout300860_1_Corrections.docxPLAN CHECK COMMENTS
COMMENTS
Planning & Building Agency
Building Safety Division
20 Civic Center Plaza
P.O. Box 1988 (M-19)
Santa Ana, CA 92702
(714) 647-5800
www.santa-ana.org
PLAN CHECK NO:
101114648
PROJECT ADDRESS:
2350 S Redhill Ave Bldg# P
PLAN CHECK ENGINEER:
Le, TungTEL:714
647-5896
EMAIL:
Tle10@santa-ana.orgFAX:714
647-5897
TYPE OF CONSTRUCTION:
I B, SPK
OCCUPANCY CLASSIFICATION(S):
A-3, S-2
PLAN CHECK DATES:
REMARKS/RECHECK ITEMS:
APPLICATION
4/13/2023
INITIAL REVIEW
7/13/2023
EXPIRATION
10/10/2023
RECHECKS:
1.
PROJECT APPLICANT CONTACT PERSON:
2.
Heidi Hare
3.
TEL:
(949)246-0492
FAX:
VALUATION:
EMAIL:
heidi@jlhare.com
FLOOD ZONE: X-0602320279J
APPLICABLE CODE: 2022 CALIFORNIA BUILDING CODE (CBC) WITH
CITY OF SANTA ANA AMENDMENTS
All items noted on this plan check report must be addressed. If you feel that an item is not applicable to your project, note “N/A” and discuss the reason with the plan checker.Please indicate the sheet number and detail to the right of each correction, or note the number on the plans where the correction is made. Resubmit marked original, calculations and this correction sheet. A separate sheet for response may be used.Resubmit 2corrected sets of plans.The applicant shall obtain clearances/approvals for the following prior to building permit issuance:
- Fire Department approval on the corrected/final sets of drawings ((714)573-6100)Sheet GA0.1.0: Deferred Submittals – The following items were removed from the previous approved plans. Please provide justification / explanation for items that were not included under the Deferred Submittals. Elevator Connection to StructureSignage Swimming Pool & SpaSpray-on FireproofingElectric Vehicle Charging Equipment Light gage metal frames Sheet GS1.1A: Deferred Submittals - The following items were removed from the previous approved plans. Please provide justification / explanation for items that were not included under the Deferred Submittals.Automatic Fire Sprinkler System and AlarmSpray-on Fireproofing Light Gauge Metal FramingTwo Way Radio Communication Emergency GeneratorDASHealth Department ….Shear Studs and Rail Assembly Per GS1.5Vehicle Barrier CableAlternative methods of Seismic Shearwall Concrete PlacementIf Separate permits are required, please provide a Separate Permits section and list all required items under separate permit.