HomeMy WebLinkAbout303231_1_Corrections.docxTENANT IMPROVEMENT
PLAN CHECK COMMENTS
COMMENTS
Planning & Building Agency
Building Safety Division
20 Civic Center Plaza
P.O. Box 1988 (M-19)
Santa Ana, CA 92702
(714) 647-5800
www.santa-ana.org
PLAN CHECK NO:
101115437
PROJECT ADDRESS:
3535 W Garry Ave
PLAN CHECK ENGINEER:
Le, TungTEL:714
647-5896
EMAIL:
Tle10@santa-ana.orgFAX:714
647-5897
TYPE OF CONSTRUCTION:
V B
OCCUPANCY CLASSIFICATION(S):
U
PLAN CHECK DATES:
REMARKS/RECHECK ITEMS:
APPLICATION
6/13/2023
INITIAL REVIEW
6/22/2023
EXPIRATION
12/10/2023
RECHECKS:
1.
PROJECT APPLICANT CONTACT PERSON:
2.
Brad Kenson
3.
TEL:
(949)228-5687
FAX:
VALUATION: $10,000.00
EMAIL:
brad@fastrackpower.com
FLOOD ZONE: X-0602320258J
APPLICABLE CODE: 2022 CALIFORNIA BUILDING CODE (CBC) WITH
CITY OF SANTA ANA AMENDMENTS
All items noted on this plan check report must be addressed. If you feel that an item is not applicable to your project, note “N/A” and discuss the reason with the plan checker.Please indicate the sheet number and detail to the right of each correction, or note the number on the plans where the correction is made. Resubmit marked original, calculations and this correction sheet. A separate sheet for response may be used.Resubmit 2corrected sets of plans.The applicant shall obtain clearances/approvals for the following prior to building permit issuance:
- Planning Division approval on the corrected/final set of drawings (647-5804.) Previously approved plans
should be submitted to expedite the process.
- Fire Department approval on the corrected/final sets of drawings ((714)573-6100). DoneSheet S1.5: Detail 1: CO2 tank detail – Please specify maximum height and diameter of the tanks. Provide CO2 tank specification.Detail 2: RO tank detail On the plan, please clearly show location of the RO tank and include in the scope of work. Please show dimensions for RO tank, including height and diameter. Provide tank specificationProvide enlarged detail to show connection of cable to angel plate to concrete footing. Provide positive connection of cables to top of tank. Structural calculation for the proposed tanks were not provided. Please provide calculation for the followingCalculation for foundation supporting the tanksCalculation for anchor connection for overturning forcesCalculation for cablesDesign for full tank and empty tank conditionSpecify special inspection is required for concrete strength, post-install anchor bolts. Sheet S2.4: Please show foundation dimensions. Provide detail between new pad and existing building footing. Show separation joist between new pad and existing structure wall/footing. Detail 12/S1.5 called out on the foundation plan was not applicable. Please verify and reference to the correct detail. Detail 12/S1.6 called out on the foundation plan was not applicable. Please verify and reference to the correct detail.(End of comment)