HomeMy WebLinkAbout303765_1_Corrections.docxTENANT IMPROVEMENT
PLAN CHECK COMMENTS
COMMENTS
Planning & Building Agency
Building Safety Division
20 Civic Center Plaza
P.O. Box 1988 (M-19)
Santa Ana, CA 92702
(714) 647-5800
www.santa-ana.org
PLAN CHECK NO:
101115580
PROJECT ADDRESS:
1529 E St Gertrude Pl
PLAN CHECK ENGINEER:
Le, TungTEL:714
647-5896
EMAIL:
Tle10@santa-ana.orgFAX:714
647-5897
TYPE OF CONSTRUCTION:
V B, SPK
OCCUPANCY CLASSIFICATION(S):
B, F-1, S-1
PLAN CHECK DATES:
REMARKS/RECHECK ITEMS:
APPLICATION
6/22/2023
INITIAL REVIEW
7/27/2023
EXPIRATION
12/19/2023
RECHECKS:
1.
PROJECT APPLICANT CONTACT PERSON:
2.
Gegam Burnazyan
3.
TEL:
(818)521-6342
FAX:
VALUATION: $15,000.00
EMAIL:
gegam@mlbengineering.org
FLOOD ZONE: X-0602320276J
APPLICABLE CODE: 2022 CALIFORNIA BUILDING CODE (CBC) WITH
CITY OF SANTA ANA AMENDMENTS
All items noted on this plan check report must be addressed. If you feel that an item is not applicable to your project, note “N/A” and discuss the reason with the plan checker.Please indicate the sheet number and detail to the right of each correction, or note the number on the plans where the correction is made. Resubmit marked original, calculations and this correction sheet. A separate sheet for response may be used.Resubmit 2corrected sets of plans.The applicant shall obtain clearances/approvals for the following prior to building permit issuance:
- Planning Division approval on the corrected/final set of drawings (647-5804.) Previously approved plans
should be submitted to expedite the process.Sheet A-1.0: Applicable Codes – Please update code edition to the 2022 Code edition. Sheet A-1.1 & A-1.2: Per structural plan and detail, there will be a partial infill of wall at the loading/unloading area on the west side of the building. Please verify and show the infill area on the plan. Structural calculation: Please revise calculation for the current code (2022 CBC) and Standards. Detail 1/S-0.57: Please provide C steel columns to support the steel header. Provide calculation. The current anchor bolt to existing CMU wall would not be sufficient. (End of Comment)