HomeMy WebLinkAbout308697_1_Corrections.docxRESIDENTIAL PLAN CHECK
COMMENTS
Planning & Building Agency
Building Safety Division
20 Civic Center Plaza
P.O. Box 1988 (M-19)
Santa Ana, CA 92702
(714) 647-5800
www.santa-ana.org
PLAN CHECK NO:
102117110
PROJECT ADDRESS:
1519 W Twelfth St
PLAN CHECK ENGINEER:
Lo, JonathanTEL:714
647-5822
EMAIL:
Jlo@santa-ana.orgFAX:714
647-5897
TYPE OF CONSTRUCTION:
V B
OCCUPANCY CLASSIFICATION(S):
R-3, U
PLAN CHECK DATES:
REMARKS/RECHECK ITEMS:
APPLICATION
10/17/2023
INITIAL REVIEW
11/22/2023
EXPIRATION
4/14/2024
RECHECKS:
1.
PROJECT APPLICANT CONTACT PERSON:
2.
Ignacio Ochoa
3.
TEL:
(714)904-4823
FAX:
VALUATION: $10,000.00
EMAIL:
ignacio.ochoa.pe@gmail.com
FLOOD ZONE: X-0602320144J
Note: Numbers in parenthesis (unless otherwise noted) refer to code sections of the 2022 California Residential Code (CRC); 2022 California Building Code (CBC); CMC = 2022 California Mechanical Code; CPC = 2022 California Plumbing Code; CEC = 2022 California Electrical Code; T = Table; ICC = International Code Council.All items noted on this plan check report must be addressed. If you feel that an item is not applicable to your project, note “N/A” and discuss the reason with the plan checker.Please indicate the sheet number and detail to the right of each correction, or note the number on the plans where the correction is made. Resubmit marked original, calculations and this correction sheet. A separate sheet for response may be used.Resubmit corrected sets of plans.Meetings between the project applicant/designer and the plan reviewer shall be by appointment only. Please call (714) 647-5822 for an appointment.
The applicant shall obtain clearances/approvals for the following, prior to building permit issuance (CHECKED BOXES REQUIRED ONLY):
☒Planning Division approval on the corrected/final set of drawings (647-5804). Previously approved plans should be submitted to expedite the process.
☐Public Works Agency approval (647-5039).
☐Fire Department approval on the corrected/final set of drawings (647-5839 or 647-5700).
☐Police Department approval on the corrected/final set of drawings (647-5840).
☐School District Approval; and a copy of the school fee worksheet, completed by the plan check engineer, shall be required by the School District to verify the scope of the work.
☐Proof of Worker's Compensation Insurance shall be required at the time of permit issuance.
☐Grading Permit. Application is made through the Building Safety Division (647-5800) and the plan review is by the Public Works Agency (647-5039).Comments have been provided on drawing and calculation hard copies in relation to all comments below. Applicant must pick up red marked sets from city prior to resubmittal and return marked up set with resubmittal.DrawingsSheet 1
Provide the following design data on the first sheet (R106.1.1)
☒Sheet Index
☒Occupancy groups (R-3/U)
☒Type of construction (V-B)
☐Automatic Fire Sprinkler (YES or NO)
☐Number of stories.
☒Flood Zone: X
☐Flood Zone: A
☐Flood Zone: AE
☐Floor area per occupancy group, including the existing structure(s)
☐Construction shall comply with the 2022 CRC, CBC, CPC, CMC, CEC, California Green Building Code, and California Energy Efficiency Standards Code editions.
Note on plan: All concealed work installed without permits must be exposed for inspection to the satisfaction of the Building Inspector. This includes methods of attachment and all footings, structural members, mechanical, electrical, plumbing and insulation.Storage shed noted to be exempt from permit is not exempt. Total square footage is to apply within application including attached patio cover which is over 120 square feet. Design is to be provided including lateral system for new storage shed.Verify if ceiling joist occurs in storage shed. It is unclear extend of ceiling joist. If occurs in storage shed, provide attic ventilation calculations and proposed ventilation.Provide details for shear transfer at all sides of storage shed. Revise note “All improvements existing except for patio beams, patio posts, and patio pads” to “All improvements existing are unpermitted to be legalized…”Provide detail for ridge beam connection at top.Provide detail/nailing for ceiling joist to roof rafter connection.Dowel new footing into existing footings. (End of Comment)