HomeMy WebLinkAbout303627_4_Corrections.docxTENANT IMPROVEMENT
PLAN CHECK COMMENTS
COMMENTS
Planning & Building Agency
Building Safety Division
20 Civic Center Plaza
P.O. Box 1988 (M-19)
Santa Ana, CA 92702
(714) 647-5800
www.santa-ana.org
PLAN CHECK NO:
101115541
PROJECT ADDRESS:
1200 E Glenwood Pl
PLAN CHECK ENGINEER:
Ahangian, KathyTEL:714
647-5812
EMAIL:
Kahangian@santa-ana.orgFAX:714
647-5897
TYPE OF CONSTRUCTION:
V B, SPK
OCCUPANCY CLASSIFICATION(S):
F-1
PLAN CHECK DATES:
REMARKS/RECHECK ITEMS:
APPLICATION
6/20/2023
INITIAL REVIEW
6/25/2023
EXPIRATION
12/17/2023
RECHECKS:
1.8/21/23
PROJECT APPLICANT CONTACT PERSON:
2.9/28/23
Eddie Terriquez
3.
TEL:
(562)659-4732
FAX:
VALUATION: $50,000.00
EMAIL:
eddie.vdc@gmail.com
FLOOD ZONE: X-0602320276J
APPLICABLE CODE: 2022 CALIFORNIA BUILDING CODE (CBC) WITH
CITY OF SANTA ANA AMENDMENTS
All items noted on this plan check report must be addressed. If you feel that an item is not applicable to your project, note “N/A” and discuss the reason with the plan checker.Please indicate the sheet number and detail to the right of each correction, or note the number on the plans where the correction is made. Resubmit marked original, calculations and this correction sheet. A separate sheet for response may be used.Resubmit2corrected sets of plans.Meetings between the project applicant/designer and the plan reviewer shall be by appointment only. Please call (714) 647-5812 for an appointment.Please return marked up set of drawings with corrections.Clearly indicate the scope of work under this building permit application:
- Construction drawings must clearly show all work to be done under the subject building permit application.Ok 8/21/23All persons preparing plans, specifications, and instruments of service for others shall sign those plans, specifications and other instruments of service for others shall sign those plans, specifications and other instruments of service and all contracts therefore. This requirement applies to both exempt and non-exempt projects. Business and Professions Code Chapter 3, Division 3, Section 5536.1(a).OK 8/21/23Include address and telephone number of the responsible designer, and date of signing of drawings.Ok 8/21/23This review does not include mechanical, plumbing, fire sprinkler system, or electrical work. Separate plans, applications, fees, plan checks, and permits are required for mechanical, plumbing, fire sprinkler systems, and electrical work. Call 647-5800 for information.The applicant shall obtain clearances/approvals for the following prior to building permit issuance:
- Planning Division approval on the corrected/final set of drawings (647-5804.) Previously approved plans
should be submitted to expedite the process.
- Public Works Agency approval (647-5039)
- Proof of Worker’s Compensation Insurance shall be required at the time of permit issuanceSubmit a signed copy of the contract showing labor and materials for all work to be done under the subject building permit application. The plan check engineer may accept the contract price as the valuation of improvements for unique/unusual projects in lieu of using a cost per square foot basis.Ok 8/21/23Drawings must be to scale and be on 18” x 24” minimum sheets.Ok 8/21/23
- Provide a Vicinity Map showing project location
- Provide a fully dimensioned Floor Plan Provide the following:Pending 8/21/23Pending 9/28/23
- Provide a fully dimensioned site plan on each set of plans. Pending 8/21/23
- Disabled access compliance must be shown on the site plan. Provide truncated dome at the door in the warehouse, provide curb ramp detail, dimension, truncated dome,… Pending 9/28/23
- Show all property lines of record on the site plan. Ok 8/21/23Show on the plans: Pending 8/21/23Ok 9/28/23- Occupancy Classification(s) Show F1 and B
- Type of ConstructionIdentify type of the material storing and type of the business.Ok 8/21/23Submit a letter addressed to the Building Safety Division describing in detail the manufacturing process from material delivery, storage, handling, packaging, and shipping of finish product. Include an equipment list describing use in the process.Ok 8/21/23Provide existing floor plan.Ok 8/21/23Provide use of the laser room. Ok 8/21/23Provide ceiling plan to show type of the ceiling and any alteration to the ceiling. Pending 8/21/23, no t-bar ceiling or drywall?Ok 9/28/23Provide typical section view detail of all new partitions and ceilings showing: Pending 8/21/23, Provide bottom track Gauge and attachment to the floor.Ok 9/28/23
- Size, spacing, and material of framing members
- Note gauge and ICC Research Report number, installation/construction requirements for metal framing
members and span table.- Heights of partition, suspended ceiling, structure above.Egress shall not pass through warehouse.. Ok 8/21/23Remove all the exit signs at the doors that are leading to the warehouse. Pending 8/21/23, Show exit signs and directional exit sign.Ok 9/28/23Show all the exit doors on the site plan.Ok 8/21/23CBC Sections 1028, EXIT DISCHARGE. That portion of a means of egress system between the termination of an exit and a public way.Ok 8/21/23CBC Section 1028.5, Access to a public way. The exit discharge shall provide a direct and unobstructed access to a public way.Ok 8/21/23Provide on the drawings a complete door schedule, showing:( Identify all the doors by door number.)Ok 8/21/23
- Door sizes (CBC Sections 11B-404)
- Hardware complying with exiting and disabled accessibility requirements Provide minimum 18” clearance to the strike edge of the door. Pending 8/21/23, please see redmarks.Ok 9/28/23Provide 12” clearance to the strike edge of door in the hallway. Pending 8/21/23, please see red marks.Ok 9/28/23CBC Section 11B404.2.7, Hand-activated door opening hardware shall be centered between 30” and 44” above the floor. Latching and locking doors that are hand activated and which are in a path of travel shall be operable with a single effort by lever-type hardware, by panic bars, push-pull activating bars, or other hardware designed to provide passage without requiring the ability to grasp the opening hardware. Locked exit doors shall operate as above in egress direction.Ok 8/21/23CBC Section 11B-404.2.9, Note on the drawings: “Maximum effort to operate doors shall not exceed 5 pounds for exterior doors and interior doors, such pull or push effort being applied at right angles to hinged doors and at the center place of sliding or folding doors. Compensating devices or automatic door operators may be utilized to meet the above standards. When fire doors are required, the maximum effort to operate the door may be increased to the minimum allowable by the appropriate administrative authority, not to exceed 15 pounds.Ok 8/21/23CBC Section 11B-404.2.10, Required the bottom 10” of all doors except automatic and sliding shall have a smooth uninterrupted surface to allow the door to beopened by a wheelchair footrest without creating a trap or hazardous condition.Ok 8/21/23CBC Section 1013.1. Provide a directional exit sign at changes in exiting direction. Pending 8/21/23 show on the floor planOk 9/28/23Tactile exit signs shall be required at the following locations:.Pending 8/21/23 show on the floor planPending 9/28/23, show on the floor plan . please see red marks on sheet A2.
- Each grade-level exterior exit door shall be identified by a tactile exit with the word “EXIT.”
- Each exit door that leads directly to a grade-level exterior exit by means of an exit enclosure, or an exit
passageway, shall be identified by a tactile exit sign with the words “EXIT ROUTE.”
- Each exit access door from an interior room or area to a corridor or hallway, which is required to have a visual
exit sign, shall be identified by a tactile exit sign with the words “EXIT ROUTE.”
- Each exit door through a horizontal exit shall be identified by a sign with the words “TO EXIT.”It is the project designer’s/property owner’s responsibility to show compliance on the drawings with all applicable Federal and State Accessibility Standards.Ok 9/28/23Drawings submitted to the Building Division for review shall provide the following information to insure compliance with CBC Section 11B-202.4:
- An accessible entrancePending Pending 9/28/23, provide path of travel to include curb ramp detail.
- An accessible route to the altered area
- Accessible restroomsPending 9/28/23, show the door encroach to the turning space not more than 12”.
- Accessible telephone (if any)
- Accessible drinking fountains, and
- Parking, signage and alarmsPending 8/21/23 show complete dimension and detail.Pending 9/28/23, Provide counter height for the kitchen to show compliance with accessibility. Pending 8/21/23 Shall be maximum 34”Ok 9/28/23 Show sink in the kitchen complies with accessibility.Pending 8/21/23 show elevation and kneeroom.Pending 9/28/23Provide a continuous walking surface from each exit door to public way. Ok 8/21/23If a walk crosses or adjoins a vehicular way, and the walking surfaces are not separated by curbs, railings or other elements between the pedestrian areas and vehicular areas, the boundary between the areas shall be defined by a continuous detectable warning which is 36” wide, complying with the CBC Section 11B-247.1.2.5.Pending 8/21/23, show on the drawings.Pending 9/28/23, is there a curb ramp ? if not provide continuous truncated dome Each lot or parking structure where parking is provided for the public as clients, guest or employees, shall provide accessible parking as required by CBC Section 11B-502. Pending 8/21/23, provide detail.Ok 9/28/23CBC Section 11B-208.2.4 One in every six accessible spaces, but not less than one, shall be served by an access aisle 8’-0” (96”) wide minimum and shall be designated van accessible as required by Section 11B-502. The words NO PARKING shall be painted on the ground within each eight’ loading and unloading access aisle. This notice shall be painted in white letters no less than 12” high and located so that it is visible to traffic enforcement officials. Pending 8/21/23, show Van accessible.Pending 9/28/23, provide detail for Van accessible and standard parking,(Please cross reference the details) Van accessible Aisle shall be on the passenger side.Provide completely dimensioned floor plans, elevations and sections of sanitary facility insuring wheelchair clearances complying with CBC Section 11B-603,11B604 and the California Plumbing Code.Pending 8/21/23, not found.Pending 9/28/23, show door cannot encroach more than 12” into the turning circle.Show minimum 48” clearance at the front of the toilet, in bathroom #3 and #4. Ok 8/21/23 Provide 60” clearance from the toilet wall to the sink.Ok 8/21/23CBC Section 1607.7. Provide complete grab bar details on the drawings showing compliance with CBC Section 1115B.8 including structural strength to support a 250 pound point load. Pending 8/21/23, Not found Pending 9/28/23, 25 Ga, is not strong enough to use as blocking.CBC Section 11B-606.5. Note on the drawings hot water and drain pipes under lavatory shall be insulated. Ok 8/21/23Show 60” landing at the bathroom doors. Not found 8/21/23, show the dimension.Ok 9/28/23Complete the attached Disabled Accessibility Documentation Form.Pending 8/21/23 Please fillout after providing parking and path of travel on the drawings.Pending 9/28/23 Not included.