HomeMy WebLinkAbout308777_1_Corrections.docxTENANT IMPROVEMENT
PLAN CHECK COMMENTS
COMMENTS
Planning & Building Agency
Building Safety Division
20 Civic Center Plaza
P.O. Box 1988 (M-19)
Santa Ana, CA 92702
(714) 647-5800
www.santa-ana.org
PLAN CHECK NO:
101117137
PROJECT ADDRESS:
302 E Goetz Ave
PLAN CHECK ENGINEER:
Ahangian, KathyTEL:714
647-5812
EMAIL:
Kahangian@santa-ana.orgFAX:714
647-5897
TYPE OF CONSTRUCTION:
V B, SPK
OCCUPANCY CLASSIFICATION(S):
B, F-1, S-1
PLAN CHECK DATES:
REMARKS/RECHECK ITEMS:
APPLICATION
10/18/2023
INITIAL REVIEW
11/27/2023
EXPIRATION
4/15/2024
RECHECKS:
1.
PROJECT APPLICANT CONTACT PERSON:
2.
Travis Hertzberg
3.
TEL:
(714)724-1252
FAX:
VALUATION: $46,000.00
EMAIL:
sales@skylitetec.net
FLOOD ZONE: X-0602320278J
APPLICABLE CODE: 2022 CALIFORNIA BUILDING CODE (CBC) WITH
CITY OF SANTA ANA AMENDMENTS
All items noted on this plan check report must be addressed. If you feel that an item is not applicable to your project, note “N/A” and discuss the reason with the plan checker.Please indicate the sheet number and detail to the right of each correction, or note the number on the plans where the correction is made. Resubmit marked original, calculations and this correction sheet. A separate sheet for response may be used.Resubmit 2corrected sets of plans.Meetings between the project applicant/designer and the plan reviewer shall be by appointment only. Please call (714) 647-5812 for an appointment.Please return marked up set of drawings with corrections.The drawings/information submitted for Building Safety Division review is incomplete. The applicant shall, prior to resubmitting, complete all construction documents to show compliance with the CBC2022, CFC 2022, CEC 2022, California Building Standards Code with local amendments.The applicant shall obtain clearances/approvals for the following prior to building permit issuance:
- Planning Division approval on the corrected/final set of drawings (647-5804.) Previously approved plans
should be submitted to expedite the process.
- Fire Department approval on the corrected/final sets of drawings ((714)573-6100)
- Police Department approval on the corrected/final set of drawings (647-5840)
- Public Works Agency approval (647-5039)
- Proof of Worker’s Compensation Insurance shall be required at the time of permit issuanceSubmit a signed copy of the contract showing labor and materials for all work to be done under the subject building permit application. The plan check engineer may accept the contract price as the valuation of improvements for unique/unusual projects in lieu of using a cost per square foot basis.Show on the plans:
- Occupancy Classification(s)
- Type of Construction
- Fire Sprinkler System Submit a letter addressed to the Building Safety Division describing in detail the manufacturing process from material delivery, storage, handling, packaging, and shipping of finish product. Include an equipment list describing use in the process.Show building envelope complies with California energy code section 140.3( to justify minimum daylighting for enclosed spaces) by reducing number of skylights. Provide inside dimension of skylight on sheet S-3 .Provide ICC report for new Skylights.Please see OCFA for the smoke vent per CBC 2022, section 410.2.7.1 and section 910.