PLAN CHECK NO:
101116485
PROJECT ADDRESS:
2018 W Lingan Ln
PLAN CHECK ENGINEER:
Le, TungTEL:714
647-5896
EMAIL:
Tle10@santa-ana.orgFAX:714
647-5897
TYPE OF CONSTRUCTION:
V B
OCCUPANCY CLASSIFICATION(S):
R-3, U
PLAN CHECK DATES:
REMARKS/RECHECK ITEMS:
APPLICATION
8/30/2023
INITIAL REVIEW
9/28/2023
EXPIRATION
2/26/2024
RECHECKS:
1.
PROJECT APPLICANT CONTACT PERSON:
2.
Fausto Funes
3.
TEL:
(818)571-2824
FAX:
VALUATION: $17,000.00
EMAIL:
gunesconstruction@yahoo.com
FLOOD ZONE: X-0602320257J
Note: Numbers in parenthesis (unless otherwise noted) refer to code sections of the 2022 California Residential Code (CRC); 2022 California Building Code (CBC); CMC = 2022 California Mechanical Code; CPC = 2022 California Plumbing Code; CEC = 2022 California Electrical Code; T = Table; ICC = International Code Council.All items noted on this plan check report must be addressed. If you feel that an item is not applicable to your project, note “N/A” and discuss the reason with the plan checker.Please indicate the sheet number and detail to the right of each correction, or note the number on the plans where the correction is made. Resubmit marked original, calculations and this correction sheet. A separate sheet for response may be used.Resubmit 3corrected sets of plans.
The applicant shall obtain clearances/approvals for the following, prior to building permit issuance:
-Planning Division approval on the corrected/final set of drawings (647-5804). Previously
approved plans should be submitted to expedite the process.
Sheet 1:
Applicable Codes: Please revise plan to specify 2022 Code edition and include 2022 CBC, CRC, CPC, CEC, CMC, 2022 California Energy Code, and 2022 California Green Building Code.
Type of construction: Please specify type V-B.
Specify on the plan Occupancy Groups: R-3 / U.
Total F.A.R: Please clarify information indicated as “(N) ADU & (N) Unit”. Revise information accordingly.
Sheet 4:
Building Section: Please revise section to show change in elevation between the interior finish floor and exterior finish slab (minimum 2”), and finish grade (8” minimum to the wood post).
On the plan, please clearly show where the building Sections were cut through.
Section 1 appears not applicable to the porch cover. Please coordinate and revise plan accordingly.
Sheet 6 & 7:
Please coordinate with structural plans; it can be removed, if duplicated information are provided.
Structural Review Comments:
Structural calculation and plans shall be stamped, signed, and dated by the engineer of record.
Detail 1/SD-1: Please revise detail to provide minimum 8” separation between the exposed earth surface and wood post.
Detail 2/SD-1: Please show change in elevation between the interior concrete slab and new exterior concrete slab (2” minimum).
(End of Comment)