HomeMy WebLinkAbout311003_1_Corrections.docxRESIDENTIAL PLAN CHECK
COMMENTS
Planning & Building Agency
Building Safety Division
20 Civic Center Plaza
P.O. Box 1988 (M-19)
Santa Ana, CA 92702
(714) 647-5800
www.santa-ana.org
PLAN CHECK NO:
101117789
PROJECT ADDRESS:
2340 N Oakmont Ave
PLAN CHECK ENGINEER:
Huang, GaryTEL:714
647-5862
EMAIL:
Ghuang@santa-ana.orgFAX:714
647-5897
TYPE OF CONSTRUCTION:
V B
OCCUPANCY CLASSIFICATION(S):
R-3, U
PLAN CHECK DATES:
REMARKS/RECHECK ITEMS:
APPLICATION
12/21/2023
INITIAL REVIEW
2/8/2024
EXPIRATION
6/18/2024
RECHECKS:
1.
PROJECT APPLICANT CONTACT PERSON:
2.
Tiffanie Le
3.
TEL:
(714)234-4525
FAX:
VALUATION: $5,500.00
EMAIL:
permits@professionalfoundationrepair.com
FLOOD ZONE: X-0602320163J
GUIDELINES:
Comments contained within this report reflect only those of the Building and Safety Division. Additional comments or corrective action may be required by other Departments and/or outside Agencies
This Plan Review Report and all subsequent code references are based upon the most recent version(s) of the 2022 California Building Codes (CBC, CRC, CFC, CEC, CPC, CMC, CGBSC, and CEES)
The approval of plans and any supporting documents does not permit the violation of any section of the adopted building codes or other pertinent local ordinances, or state and federal laws
All listed plan review comments must be adequately addressed before a building permit can be issued
Please indicate the sheet number and detail to the right of each correction, or note the number on the plans where the correction is made. Resubmit marked original, calculations and this correction sheet. A separate sheet for response may be used.
PLAN REVIEW COMMENTS:
Applicant shall address all the checked‘☒’ correction comments below before resubmitting plans to Building Safety for recheck.
☒1. The applicant shall obtain clearances/approvals for the following, prior to building permit issuance:
☒Planning Division approval on the corrected/final set of drawings (647-5804). Previously approved plans should be submitted to expedite the process.
☐Fire Department approval on the corrected/final set of drawings (647-5839 or 647-5700).
☐Police Department approval on the corrected/final set of drawings (647-5840).
☐Public Works Agency approval (647-5039).
☐Proof of Worker's Compensation Insurance shall be required at the time of permit issuance.
☐School District Approval; and a copy of the school fee worksheet, completed by the plan check engineer, shall be required by the School District to verify the scope of the work.
☐Grading Permit. Application is made through the Building Safety Division (647-5800) and the plan review is by the Public Works Agency (647-5039).☒Additional Review Comment:
Sheet A01
Applicant to verify layout. The remodel area from sheet A01 is different from Sheet 3. Revise sheet to match site condition
Sheet 2
Are all post and beam going to be new construction? Identify all floor framing on plan. See sheet 3 for more comments
Sheet 3
Please clarify all legend and provide/identify all size of floor framing, spacing of framing, post and pier spacing.
At the lower left corner of the building, are the post and pier be replaced per legend? Provide structural calculation indicate (N) post and spacing are adequate
Provide minimum edge distance for URFP from wall ends, typical all location
Verify spacing of “URFP” with table 5
Sheet 4
Provide wood screws size and number of screw required per plate per location
Provide adhesive or expansion anchor size, manufacture and ICC report
Provide minimum edge distance required
Identify height of cripple wall below floor.
Red marked comment set is available to pick-up at the City Hall.(End of Comment)