HomeMy WebLinkAbout311358_2_Corrections.docxTENANT IMPROVEMENT
PLAN CHECK COMMENTS
COMMENTS
Planning & Building Agency
Building Safety Division
20 Civic Center Plaza
P.O. Box 1988 (M-19)
Santa Ana, CA 92702
(714) 647-5800
www.santa-ana.org
PLAN CHECK NO:
101117900
PROJECT ADDRESS:
3 E Hutton Center Dr Unit# 150
PLAN CHECK ENGINEER:
Le, TungTEL:714
647-5896
EMAIL:
Tle10@santa-ana.orgFAX:714
647-5897
TYPE OF CONSTRUCTION:
I A, SPK
OCCUPANCY CLASSIFICATION(S):
B
PLAN CHECK DATES:
REMARKS/RECHECK ITEMS:
APPLICATION
1/9/2024
INITIAL REVIEW
1/20/2024
EXPIRATION
7/7/2024
RECHECKS:
1.
PROJECT APPLICANT CONTACT PERSON:
2.
Judy Yam
3.
TEL:
(626)675-9882
FAX:
VALUATION: $198,765.00
EMAIL:
meiyeeyam@sbcglobal.net
FLOOD ZONE: X-0602320278J
APPLICABLE CODE: 2022 CALIFORNIA BUILDING CODE (CBC) WITH
CITY OF SANTA ANA AMENDMENTS
All items noted on this plan check report must be addressed. If you feel that an item is not applicable to your project, note “N/A” and discuss the reason with the plan checker.Please indicate the sheet number and detail to the right of each correction, or note the number on the plans where the correction is made. Resubmit marked original, calculations and this correction sheet. A separate sheet for response may be used.Resubmit 2corrected sets of plans.The applicant shall obtain clearances/approvals for the following prior to building permit issuance:
- Planning Division approval on the corrected/final set of drawings (647-5804.) Previously approved plans
should be submitted to expedite the process.
- Fire Department approval on the corrected/final sets of drawings ((714)573-6100)
- Police Department approval on the corrected/final set of drawings (647-5840)
- Public Works Agency approval (647-5039)
An application for a permit for any proposed work shall be deemed to have abandoned / expired after 180 days of the date of filing, unless such application has been issued. Sheet A0.1: Drawing Index: Please specify on the plan Mechanical, Plumbing and Electrical, are under separate review and approval. Sheet A0.6: Please provide enlarged accessible parking stalls and details to show accessible parking stalls are in compliance with the current code, 2022 CBC. Details shall be clearly cross-referenced onto the plan. Please provide details of truncated domes to show compliance with the current code, 2022 CBC. Details shall be clearly cross-referenced onto the plan. Sheet A0.7: Please clarify whether there is a door at the second exit access (on the left side of the suite, adjacent to the pantry area). Door shall swing in the direction of travel. For clarity, please show exit access continue to the exit discharge. Note E1: Please show existing restrooms accessible to the persons with disabilities, complying with Chapter 11B, Division 6. Restroom floor plans and details shall be clearly cross-referenced onto the plan where it’s applicable. Sheet A2.0: All glass wall panels shall be temper glass. New wall construction: Please clearly cross-reference wall construction details onto the plan for each wall type. Glass wall panels: Provide structural calculation and details for support of the glass wall panel. For example, wall at the conference room. Sheet A4.0: Please specify minimum ceiling height at the Lobby area, and provide construction details for the ceiling finish above the Lobby. Sheet A7.0 & A7.1: Wall details and ceiling details shall be clearly cross-referenced onto the plan where it’s applicable. Delete detail that does not applicable. (End of Comment)