HomeMy WebLinkAbout307367_3_Corrections.docx PLAN CHECK
COMMENTS
Planning & Building Agency
Building Safety Division
20 Civic Center Plaza
P.O. Box 1988 (M-19)
Santa Ana, CA 92702
(714) 647-5800
www.santa-ana.org
PLAN CHECK NO:
104116646
PROJECT ADDRESS:
2525 S Birch St
PLAN CHECK ENGINEER:
Huang, GaryTEL:714
647-5862
EMAIL:
Ghuang@santa-ana.orgFAX:714
647-5897
TYPE OF CONSTRUCTION:
V B
OCCUPANCY CLASSIFICATION(S):
B, M, S-1
PLAN CHECK DATES:
REMARKS/RECHECK ITEMS:
APPLICATION
11/6/2023
INITIAL REVIEW
1/2/2024
EXPIRATION
5/4/2024
RECHECKS:
1.
PROJECT APPLICANT CONTACT PERSON:
2.
Filiberto Benavides
3.
TEL:
(951)741-3525
FAX:
VALUATION: $5,000.00
EMAIL:
Filibertob@kushagram.com
FLOOD ZONE: X-0602320278J
Note: Numbers in parenthesis (unless otherwise noted) refer to code sections of the 2022 California Residential Code (CRC); 2022 California Building Code (CBC); CMC = 2022 California Mechanical Code; CPC = 2022 California Plumbing Code; CEC = 2022 California Electrical Code; T = Table; ICC = International Code Council.
APPLICABLE CODE: 2022 CALIFORNIA BUILDING CODE (CBC) WITH
CITY OF SANTA ANA AMENDMENTSThe applicant shall obtain clearances/approvals for the following, prior to building permit issuance:☐Planning Division approval on the corrected/final set of drawings (647-5804). Previously approved plans should be submitted to expedite the process.☐Fire Department approval on the corrected/final set of drawings (647-5839 or 647-5700). ☐Police Department approval on the corrected/final set of drawings (647-5840).☐Public Works Agency approval (647-5039).☐Proof of Worker's Compensation Insurance shall be required at the time of permit issuance.☐School District Approval; and a copy of the school fee worksheet, completed by the plan check engineer, shall be required by the School District to verify the scope of the work.☐Grading Permit. Application is made through the Building Safety Division (647-5800) and the plan review is by the Public Works Agency (647-5039).All items noted on this plan check report must be addressed. If you feel that an item is not applicable to your project, note “N/A” and discuss the reason with the plan checker.Clearly indicate scope of work to be done under this building permit application. Identify all changes on plan. Room name identify on scope of work shall be consistent with room name on the construction document. List all changes for the room names e.g. legalized (12) 8’-0” high storage rack; delivery room #1 used as admin office.
[Comment resolved]Provide building information on plan, e.g. sheet index, occupancy classification, type of construction, automatic fire sprinkler (Yes or No), number of storie[Comment resolved]Provide/specify on plan the occupancy use for the adjacent suit[Comment resolved]Provide on plan fire rating for the demising wall Show detail summary of the floor area and all deduction for gross and/or net area (CBC 1004.1[Comment NOT resolve – provide fired rated hour for the demising wall]Show the path of exist travel on proposed plan & indicate exist access travel distance. [Comment resolved]Show and dimension common path of travel at most critical condition[Comment NOT resolve – maximum common path of travel for M occupancy is 75’-0”]Provide and indicate on plan the accessible service counter per CBC Ch 11B-904.4[Comment resolved]Provide drawing to scale for both existing floor plan and proposed floor plan [Comment resolved]Revise typical dimension on the proposed floor plan that are not legible [Comment resolved]Indicate on plan for the accessible bathroom compartment fixture dimension and grab bar complying with CBC Ch 11B-604 [Comment resolved]Identify the item for two dimension (30’-8”L x 2’-0”W x 8’-0”H, and 12’-0”L x 2’-0”W x 8-0” H) on plan in the delivery area. Are those shelve/counter? [Comment resolved]Provide calculation for post-install anchor design for the 8’-0” storage rack and indicate the required anchorage detail on construction document including its dimeter, embedment, and ICC-ESR report number. [Comment NOT resolveProvide structural calculation for post-install anchor design per ACI 318-19Provide construction document detail for rack anchorage including diameter, embedment and ICC-ESR report number]Red marked comment set is available to pick-up at the City HallAdditional Review Comment 2/12/2024:CBC Sections A106.1 and A106.3.4.1, All drawings and supporting documents shall be prepared, stamped and signed by a California licensed architect or registered civil engineer.