HomeMy WebLinkAbout315370_3_Corrections.docxTENANT IMPROVEMENT
PLAN CHECK COMMENTS
COMMENTS
Planning & Building Agency
Building Safety Division
20 Civic Center Plaza
P.O. Box 1988 (M-19)
Santa Ana, CA 92702
(714) 647-5800
www.santa-ana.org
PLAN CHECK NO:
101119147
PROJECT ADDRESS:
1 E MacArthur Pl Unit# 800
PLAN CHECK ENGINEER:
Ahangian, KathyTEL:714
647-5812
EMAIL:
Kahangian@santa-ana.orgFAX:714
647-5897
TYPE OF CONSTRUCTION:
I A
OCCUPANCY CLASSIFICATION(S):
A-3, B
PLAN CHECK DATES:
REMARKS/RECHECK ITEMS:
APPLICATION
5/6/2024
INITIAL REVIEW
5/18/2024
EXPIRATION
11/2/2024
RECHECKS:
1.
PROJECT APPLICANT CONTACT PERSON:
2.
Gabi Martinez
3.
TEL:
(213)929-1404
FAX:
VALUATION: $100,000.00
EMAIL:
mgartinez@saaia.com
FLOOD ZONE: X-0602320278J
APPLICABLE CODE: 2022 CALIFORNIA BUILDING CODE (CBC) WITH
CITY OF SANTA ANA AMENDMENTS
All items noted on this plan check report must be addressed. If you feel that an item is not applicable to your project, note “N/A” and discuss the reason with the plan checker.Please indicate the sheet number and detail to the right of each correction, or note the number on the plans where the correction is made. Resubmit marked original, calculations and this correction sheet. A separate sheet for response may be used.Resubmit 2corrected sets of plans.Meetings between the project applicant/designer and the plan reviewer shall be by appointment only. Please call (714) 647-5812 for an appointment.Please return marked up set of drawings with corrections.Clearly indicate the scope of work under this building permit application: (Removal of stairways connecting 8th floor and 9th floor)
- Revise project job description on the building permit application worksheet to reflect the work to be done
under the subject building permit application.The applicant shall obtain clearances/approvals for the following prior to building permit issuance:
- Planning Division approval on the corrected/final set of drawings (647-5804.) Previously approved plans
should be submitted to expedite the process.
- Public Works Agency approval (647-5039)Show on the plans:
- Project Address/Suite/Room Numbers; Building Numbers ( Provide suite number for both 8th and 9th floor)Show the center of the street on the site plan.No truncated domes allowed on the access aisle. Please identify how many units at each floor with address.Provide typical section view detail of all new partitions and ceilings showing;
- Method of attaching framing to the building structure. Compliance shall be shown with CBC Section 1607.13
for lateral support of the walls. Do not support top of walls to suspended ceiling system unless calculations
and drawing prepared by a registered engineer are submitted for review. Submit structural engineering
calculations for walls in rooms with a floor to building structure above height greater than 14
- Heights of partition, suspended ceiling, structure above.Provide complying exiting plan for the 9th floor. ( after removing the stairways)EXIT ACCESS. That portion of a means of egress system that leads from any occupied portion of a building or structure to an exit. Provide span table for the metal studs.Show bathrooms on the 8th floor complies with accessibility.Show ceiling plan for the 8th and show if there is any opening on the 8th floor ceiling.Show exact condition for detail 2/A2-0, is it sitting on the beam?Provide height of the partition to the structure above on detail 2/A2.0.Minimum width for the Van accessible parking is 9’. Please revise detail on sheet A-0.5A.Show minimum 12” clearance to the strike edge of the men’s bathroom and 48” landing at the door. Please see red mark.